9
8.
It can take up to 2 minutes for the SSOs to show up in the
status list.
9.
When all SSOs have been detected, go ahead and activate PV
production and ACE functionality. Follow steps
17 to 23
in
section
1 EnergyHub
, select
ACE & PV
instead.
NOTE!
It can take up to 10 minutes for the SSOs to start producing
after being detected and activated.
10.
check the status of each SSO by one of the following methods:
a.
Go to the SSOs and look at the LED indicator status.
b.
Press serial number in SSO status view, check for
correct string voltage and that the SSO is delivering
power.
c.
If the system is registered in the EnergyCloud, log
look to see that all SSOs are delivering power.
11.
When you have verified that the SSOs are up and running go
through all check points in the
installer verification
under the
section
after commissioning
. Sign the document before
proceeding.
12.
Commissioning is now completed! To register the system in
the Ferroamp EnergyCloud follow the instructions in the
EnergyCloud registration
booklet.
3
Ene Battery
1.
Make sure that the DC breakers that disconnect your batteries
from the DC nanogrid are open (for ex. a Power Distribution
5/8/15).
2.
Follow steps
1 to 23
in section
1 EnergyHub
. When complete
proceed with the following instructions.
3.
Measure the DC voltage by the DC breaker that disconnects
your battery, this must be done on all your DC distribution
boxes that connect units to the DC nanogrid:
a.
Check that the polarity is correct (L+ and L-) and the
voltage is in the range 585
–
780 VDC.
4.
If the polarity and voltages are correct go ahead and turn on
the DC breakers.
5.
Register the system in the Ferroamp EnergyCloud, follow the
instructions in the
EnergyCloud registration
booklet.
6.
To activate and configure your battery you must contact
Ferroamp support at
following information:
a.
Facility ID
b.
Installed PV
c.
Size of main fuse
d.
Battery configuration:
i.
Maximize self-consumption of PV
ii.
Protect your main fuse
iii.
Increase power for EV charging
iv.
Peak shaving
7.
Go through all check points in the
installer verification
under
the section
after commissioning
. Sign the document before
proceeding.
8.
Commissioning is now completed!
4
Ene SSO + Battery
1.
Make sure that the DC breakers that disconnect your batteries
and SSOs from the DC nanogrid are open (for ex. a Power
Distribution 5/8/15).
2.
Follow steps
1 to 16
in section
1 EnergyHub
.
3.
Follow steps
3 to 10
in section
2 Ene SSO.
4.
Follow steps
3 to 6
in section
3 Ene Battery.
5.
Go through all check points in the
installer verification
under
the section
after commissioning
. Sign the document before
proceeding.
6.
Commissioning is now completed!