INTERIOR RAFTER ASSEMBLY
Complete the following steps 

for the interior rafters

1.  Select the pipes for the first interior rafter assembly and 

position these on the ground as shown. 

 

IMPORTANT:

 Interior rafters do not use end clamps. 

Instead, cross connectors are attached during the 

frame assembly.

2.  Insert the swaged ends of the rafter pipes into the plain 

ends of the pipes and secure each joint with a Tek 

screw. 

 

NOTE:

 For longer frames, it may be easier to assemble 

a few rafters at a time and then begin to assemble the 

frame. Position Tek screws so they will not contact the 

cover when the frame is assembled.

3.  Once rafters are assembled, assemble the frame.

FRAME ASSEMBLY

After all ground posts are driven in place and rafters are 

assembled, assemble the frame. 

NOTE: 

The baseboards (strongly recommended) shown in 

the diagrams throughout these instructions are not included 

and must be supplied by the customer.

 

Contact Customer service at 1-800-245-9881 to purchase 

baseboards, or for additional information. 

ASSEMBLE AND PRE-MARK THE PURLINS 

The following steps describe one way to speed the 

assembly process and eliminate the need to measure each 

purlin as it is installed. Pre-marking the purlins ensures that 

an accurate spacing of the rafter assemblies is achieved 

and maintained during assembly. 

Gather the Parts:
•  Pipe 1.315'' x 75'' swaged (#131S075)
•  Pipe 1.315'' x XX'' plain (#131P0XX)
•  Marker and tape measure

 

NOTE:

 The purlins are part of the assembled frame and 

run perpendicular to the rafter assemblies. Each purlin 

consists of 1.315" x 75" (#131S075) swaged pipes (number 

is determined by shelter length) and one (1) 1.315" x XX" 

(#131P0XX) plain pipe. 

 

ATTENTION:

 The XX" represents the remaining length 

required to reach the end of the shelter. Consult the Spec 

Sheet for part identification.
1.  Select the required pipe sections for one purlin and 

connect these by inserting the swaged ends of the 

pipes into the plain ends until the entire purlin is 

assembled. 

 

NOTE:

 Assemble the purlins in a location that is 

accessible during the assembly of the frame, but will 

not interfere with the process of lifting and setting the 

rafters.

2.  Verify that each pipe joint is properly seated. 

 

NOTE:

 These pipes must be separated during the 

assembly procedure. Do not fasten them together at 

this time.

3.  For the 48" rafter spacing, measure forty-eight and 

three-quarters inches (48-3/4") from one end of the 

assembled purlin and mark the distance on the pipe. 

 

NOTE:

 This first measurement is three-quarters (3/4) 

of an inch longer than the on-center rafter spacing 

to account for the length of purlin pipe that extends 

through the end purlin clamp of the first end rafter.

RAFTER ASSEMBLY (continued)

Содержание Growers Supply GrowSpan Gothic Pro Series

Страница 1: ...W x 10 H x 20 L 104849 18 W x 10 H x 24 L 104850 18 W x 10 H x 28 L 104851 18 W x 10 H x 32 L 104852 18 W x 10 H x 36 L 2018 Growers Supply All Rights Reserved Reproduction is prohibited without permi...

Страница 2: ...ions will help you determine whether your selected location is the best location Never erect the structure under power lines Identify whether underground cables and pipes are present before preparing...

Страница 3: ...rafter pipe In some cases band clamps are also used to connect diagonal struts to the assembled frame Clip or Fabric Clip A short half section piece of conduit cut lengthwise used to secure the end p...

Страница 4: ...Quick Start Guide show exploded views of all critical connections Use the diagrams in the Quick Start section to assemble the frame of your building Consult the remainder of these instructions for imp...

Страница 5: ...212 Fabric Clip FA4482B Tek Screw QH1402 Band Clamp 102548 Cross Connector 104074 Square to Round Tube Connect Bracket 102856 End Clamp FAH009B FALB01B Carriage Bolt Hex Nut 103496 Gearbox 104624 Squa...

Страница 6: ...does not allow channel side out installation Use the diagrams on this page to install H channel with flat side facing out ATTENTION Use only 1 1 2 Tek screws to attach H channel to building frame Do...

Страница 7: ...Purlins Ground Post Frame length may differ from actual frame OVERVIEW This section describes assembling your greenhouse For details please see section Assembling the Gothic Pro Greenhouse Components...

Страница 8: ...round post 6 Repeat the same step for the last corner post NOTE The distance measured diagonally between corner posts must be equal for the building to be square 7 Check all dimensions and adjust if n...

Страница 9: ...are set onto the ground posts 1 Select the five 5 pipes needed to assemble the first end rafter and arrange on a level surface 2 Slide four 4 end purlin clamps two on each side of the peak over the r...

Страница 10: ...king the purlins ensures that an accurate spacing of the rafter assemblies is achieved and maintained during assembly Gather the Parts Pipe 1 315 x 75 swaged 131S075 Pipe 1 315 x XX plain 131P0XX Mark...

Страница 11: ...Cross connector 102548 5 16 x 2 1 2 machine bolts and 5 16 nuts Lifts ladders and assistants Rope or cable 1 Carefully stand the first end rafter slide a band clamp onto each rafter leg and place the...

Страница 12: ...nter of the rafter to maintain the proper spacing Interior Rafter Align mark with center of rafter Purlin 11 Verify that the rafter spacing is forty eight inches 48 on center adjust as needed and tigh...

Страница 13: ...and is attached at ground level along both sides of the frame It helps keep the ground posts in place and also prevents the frame from working into the ground when anchored Attach the baseboards to t...

Страница 14: ...ponsible for providing a baseboard for this frame If no baseboard is present attach the strut to the ground post using a Tek screw or other customer supplied fasteners 4 Repeat the above steps to atta...

Страница 15: ...iding where to install the additional horizontal framing for accessories Consult the diagrams in the Quick Start section showing the polycarbonate panel locations and the locations of the aluminum tri...

Страница 16: ...he distance between the top of the base tube and band clamp Step 7 to determine the length of the first door jamb NOTE If the measured length is longer than 99 an additional section of square tubing i...

Страница 17: ...r length for the width of the rough door opening 20 Using two angle brackets attach the header tube to the end wall assembly between the door jambs as shown below 21 Verify that both door jambs are pl...

Страница 18: ...ning frame member 26 Choose a square to round tube connect bracket and attach the bracket to one end of the vertical frame member Use a 5 16 drill bit to drill a hole through the tube and attach the b...

Страница 19: ...eight determined by the installation instructions included with that accessory using QH1330 brackets Dashed lines show where additional frame tubes are installed If you are not installing any accessor...

Страница 20: ...nlight will make the film difficult if not impossible to remove During preparation rest the edges of the panels on cardboard or other material to protect them from dirt and damage Seal the bottom edge...

Страница 21: ...r of 4 x 12 panel is used to cover the area along other side of door Always remove protective film and mark and install UV protected side to outside of greenhouse 3 Apply white vent tape to bottom of...

Страница 22: ...ure and cut two sections of H channel to correct length H channel is used to join two separate panels Install H channel with flat side out NOTE Cut panel to proper height after attaching to end wall f...

Страница 23: ...nd prepare a panel as previously described to cover remaining area along door Use the remainder of 4 x 12 panel from Panel A End Cap 104548 H channel Install flat side out Trimmed polycarbonate panel...

Страница 24: ...TTENTION The U channel profile 104213 for top edge of all panels dashed line below is installed last and after all profile is installed along edges and between each panel b Distance between notches is...

Страница 25: ...results Consult the diagram below for clarification 2 Attach one section of the poly latch U channel to the side of the frame using Tek screws Attach U channel flush with the outside edge of the end...

Страница 26: ...or straps near the edge of the material and below where the cover will be secured to the U channel 3 After tying the ropes to the main cover throw the ropes over the top of the greenhouse and pull th...

Страница 27: ...in place 9 Move to the other end of the building and repeat the steps to secure the main cover in the U channel 10 After the cover is stretched end to end and secured using the spring and U channel mo...

Страница 28: ...d to the frame NOTE The number of pipes used in the roll up conduit assembly varies with the length of the greenhouse Roll up conduit assemblies consist of multiple sections of swaged 1 315 pipe at 75...

Страница 29: ...rial to the conduit with Tek screws and fabric clips evenly spaced along the conduit 4 Continue to roll the conduit until the excess cover material is wound around the conduit 5 Repeat these steps for...

Страница 30: ...bearing bracket and attach the bearings as needed In some instances the bearings may come already attached Assemble as follows NOTE Single bearings are attached to the sides of the bracket and double...

Страница 31: ...nt it on the same side of the mounting bracket 14 Finish rolling the cover conduit in a clockwise motion up to the Twist of the Wrist assembly INSTALL ANTI BILLOW ROPES Gather the Parts Eyebolts Anti...

Страница 32: ...no wood baseboard is present as required additional steps must be take to anchor the lower portion of the anti billow ropes 3 Move up the same end rafter and install the second eyebolt through the pol...

Страница 33: ...OUSES AND SYSTEMS Revision date 06 20 18 QUICK START GUIDE 18 Gothic Pro Greenhouse Frame shown may differ in length from actual frame Ground Level Height 18 0 9 6 15 16 Width 3 11 Sidewall Height FRO...

Страница 34: ...5 18G16B Purlin Connection Notes Purlin connected to end rafter using 102856 clamp Purlin connected to mid rafters using 102548 connector Purlin connection See Connection Note Purlin connection See Co...

Страница 35: ...EENHOUSES AND SYSTEMS Revision date 06 20 18 SIDE PROFILE 104848 131S075 131S075 131S075 Purlin Run 131P0255 4 0 on center Rafter Spacing 20 0 Length center to center Customer Supplied Baseboard Custo...

Страница 36: ...HOUSES AND SYSTEMS 36 Revision date 06 20 18 SIDE PROFILE 104849 131S075 131S075 131S075 Purlin Run 131P0735 4 0 on center Rafter Spacing 24 0 Length center to center Customer Supplied Baseboard Custo...

Страница 37: ...OUSES AND SYSTEMS Revision date 06 20 18 SIDE PROFILE 104850 28 0 Length center to center 131S075 131S075 131S075 Purlin Run 131S075 131P0495 4 0 on center Rafter Spacing Customer Supplied Baseboard C...

Страница 38: ...ND SYSTEMS 38 Revision date 06 20 18 32 0 Length 131S075 131S075 131S075 Purlin Run 131S075 131S075 131P0255 center to center 4 0 on center Rafter Spacing SIDE PROFILE 104851 Customer Supplied Baseboa...

Страница 39: ...S AND SYSTEMS Revision date 06 20 18 36 0 Length 131S075 131S075 131S075 Purlin Run 131S075 131S075 131P0735 center to center 4 0 on center Rafter Spacing Customer Supplied Baseboard Customer Supplied...

Страница 40: ...SYSTEMS 40 Revision date 06 20 18 CONNECTIONS Endwall Baserail Connection View 1 Rafter Base Rail Connection View 2 Rafter Endwall Connection View 3 Purlin End Rafter Connection View 4 Purlin Mid Raf...

Страница 41: ...ction View 4 Purlin End Rafter Connection View 2 Rafter Base Rail Connection View 5 Purlin Mid Rafter Connection View 3 Rafter Endwall Connection QH1402 1 66 Band Clamp Endwall Rafter 104074 Sq Rnd Tu...

Страница 42: ...END FRAME DIAGRAM FRONT VIEW 82 1 4 INSDIE DIM 37 5 8 C L C L 21 3 16 C L C L 21 3 16 C L C L NOTE COLUMNS NOT DIMENIONED HAVE A NON CRITICAL PLACEMENT AND ARE USED FOR POLYCARBONATE SUPPORT ALL END...

Страница 43: ...06 20 18 END FRAME DIAGRAM BACK VIEW 37 5 8 C L C L 21 3 16 C L C L 21 3 16 C L C L NOTE COLUMNS NOT DIMENIONED HAVE A NON CRITICAL PLACEMENT AND ARE USED FOR POLYCARBONATE SUPPORT ALL END FRAMING TU...

Страница 44: ...l does not allow channel side out installation Use the diagrams on this page to install H channel with flat side facing out ATTENTION Use only 1 1 2 Tek screws to attach H channel to building frame Do...

Страница 45: ...NATE PANELS FRONT VIEW USE 4 X 12 PANEL TO COVER A B H CHANNEL U CHANNEL PANEL A PANEL B 6 X 10 POLY POLY 6 X 10 POLY 4 X 8 END CAP ABOVE DOOR ONLY NOTE INSTALL UV PROTECTED SIDE OF PANEL TO THE OUTSI...

Страница 46: ...S AND SYSTEMS 46 Revision date 06 20 18 POLYCARBONATE PANELS BACK VIEW USE 4 X 12 PANEL TO COVER A B H CHANNEL PANEL A PANEL B 6 X 10 POLY POLY 6 X 10 POLY 4 X 12 NOTE INSTALL UV PROTECTED SIDE OF PAN...

Страница 47: ...47 GROWSPAN GOTHIC PRO GREENHOUSES AND SYSTEMS Revision date 06 20 18 Page reserved for customer notes...

Отзывы: