min 40
min.
0
min.
50
57
A
580
290
290
290
a
a
A
B
90°
90°
ENGLISH
5
2) Position the bearing case level, respecting the indications in
figure 7.
The centre of the hole on the case must be perfectly aligned
with respect to the leaf rotation axis.
Take a PVC tube with
6
mm diameter to route the power cable.
Insert it in the hole on the bearing case (Fig.1 ref.
q
) and take it
to the electronic control unit. (See figure 8)
Provide a 50 diameter drain pipe, for rain water, so that it arrives
at the nearest sewage channel (fig.8).
4) Wall the bearing case in the foundation pit.
Fig.7
5.3 FITTING THE GATE
NOTE:
Before you do this job, wait for the cement
in the foundation pit to set.
Fig.9
5.3.1 OPERATOR CBAC-SB
1) Dig a foundation pit as shown in Fig. 6.
Fig.6
NOTE: 1) To avoid the pit surface sinking, we advise
you, according to the soil, to make a preparatory
bottom over which to pour quick-setting cement.
2) Fit a rain water drain pipe on the
bearing case, reaching the nearest sewer, as shown
in Fig. 8 for example
LEAF ROTATION AXIS
LEAF ROTATION AXIS
1) Make the gate guide bracket, with a “U” profile with dimensions
as in figure 9.
Fig.5
GUIDE
BRACKET
DRAIN
PIPE
Fig.8
1) Decide on the correct position of the bush, referring to the
position of the leaf with respect to the rotation axis, as shown in
Fig. 10-11
TUBE IN PVC FOR
OPERATOR POWER
CABLE
CONTROL
UNIT
“A” MEASUREMENT (mm)
Without
mechanical
release
With
mechanical
release
26
47
LEAF ROTATION
AXIS
GUIDE BRACKET MID-POINT
NOTE: To exploit the operator’s entire rotation, the
bearing case must be installed perpendicularly with
respect to the closed position of the gate - as shown
in Fig. 5.
Fig.10