Sections A and B below are relevant to a changeover PDU. Section C below is relevant to both changeover and 

single inlet versions. 

A. Supply LEDs when not alarming 

A1. Off = not present 
A2. Green = present and selected 
A3. Red solid = present, standby with sync change possible in the past ten seconds 
A4. Green short flash to off = okay selected but non-sync throughout last ten seconds 
A5. Red short flash to off = okay standby but non-sync throughout last ten seconds 

B. Supply LEDs when alarming 

B1. Off = not present, i.e. failed 
B2. Green short flash to red = selected but supply failed and returned 
B3. Red short flash to green = standby but failed and returned 
B4. Green short flash to red then off = B2 + A4 
B5. Red short flash to green then off = B3 + A4 

C. Channel output LEDs 

C1. Off = channel off 
C2. Green = channel on and good 
C3. Red = fuse fail* 
C4. Flashing green = output on, should be off, relay stuck 
C5. Flashing red = channel on, fuse good but relay no good 
C6. Multiple channel LEDs flashing green to amber = unit in alarm mode. (See paragraph two above) 

* If all channel LEDs are red then this could mean a couple of things.  

1. The selected supply is wired Live Neutral reversed. This can be checked by looking at the Neutral/Earth 

reading on the OLED display (Input > i > 

 or 

 to scroll to Neutral Earth reading). On a changeover PDU, 

the display will alternate between ‘A’ supply and ‘B' Supply readings. 

2. The PDU does not have a good earth. 

Preferred Supply 

eyePower PDU are designed for use on two synchronous and phase coherent supplies. The ‘A’ supply is preferred, 
in that it will always switch back to the ‘A’ supply if it is present. 

Change from ‘A’ to ‘B’ occurs on loss of the ‘A’ supply. Change from ‘B’ to ‘A’ occurs when both supplies have been 
stable for at least ten seconds. If non-sync supplies are slowly "running through" at different frequencies, i.e. not 
locked out of sync, then change to preferred will occur when the two supplies are coincident. This could be a long 
time, but as one example, free-running generator vs mains can be surprisingly quick. 

If the two supplies are permanently out of sync, i.e. two phases of a three-phase supply, then the ‘A’ to ‘B’ 
operation will work as normal on ‘A’ supply fail, but the unit will never switch back to the ‘A’ supply when it returns. 
Switching over to the ‘A’ supply can be forced by removing the ‘B’ supply inlet completely (preferred method) or 
removing the fuse marked “B” on the front panel. Note the latter does not disconnect the ‘B’ supply, but makes the 
internal electronics think that it has disappeared. 

Содержание PDU

Страница 1: ...wer PDU User Manual Version 1 0 15th December 2021 SAFETY NOTICE End users must be made aware that power outlets are remote controlled This unit is not certified for safety isolation of the electrical supply ...

Страница 2: ...put wired direct to the 10A IEC outlets Standard relays are preferred this latest unit reduces relay power consumption and heating by 70 Relays hardly get warm using PWM a technique now favoured in the automotive industry to save energy Voltage Presence Detect Supply voltage is detected after each fuse and after each relay using a circuit which consumes 0 25W total for over 30 measurements Some ot...

Страница 3: ...tly OLED Display A full colour front panel display allows menu driven access to unit status that will change over time to meet users needs Ethernet Custom developed 10 100Mbit Ethernet module with PoE as standard that can power the entire unit and provide status data through power failure or brown out The powerful 32 bit processor will meet the demands of future developments There is a software ro...

Страница 4: ...et changeover versions eyePower changeover PDU have two inlets which are labelled A B Failure of A will cause changeover to B On return of A when both supplies have been stable for ten seconds and the two supplies are synchronous for one mains zero crossing an eyePower PDU will change back to A automatically Note this delay can be changed using eyePower Limited s Windows software via the serial po...

Страница 5: ...Live Neutral reversed This can be checked by looking at the Neutral Earth reading on the OLED display Input i or to scroll to Neutral Earth reading On a changeover PDU the display will alternate between A supply and B Supply readings 2 The PDU does not have a good earth Preferred Supply eyePower PDU are designed for use on two synchronous and phase coherent supplies The A supply is preferred in th...

Страница 6: ...eatly minimise the change of arcing between supplies all input and output relays are briefly opened hence a total of nineteen relays operate at the same time Notes THIS UNIT MUST BE EARTHED THIS UNIT IS DESIGNED FOR EUROPEAN STANDARD TYPE TN MAINS WITH NEUTRAL NEAR TO SAME POTENTIAL AS EARTH 220V 240V NOMINAL INLETS ARE 16A AND ALL INTERNAL WIRING IS RATED FOR 20A MAXIMUM UPSTREAM SUPPLY MUST BE F...

Отзывы: