Chapter 3: Preinstallation Checklist
Before you install the ERS 3600 Series, make sure that you complete the tasks in the preinstallation
checklist.
No.
Task
Description
1.
Review the technical specification for
the switch. Make sure that the area
where you install the switch and
where it will operate meet the
requirements.
For the physical, electrical, and
environmental specifications, see
2.
Verify the AC power specifications.
See
on page 17.
3.
Make sure that you have the
following tools and cables:
• Phillips #2 screwdriver RJ-45
console port cable
• ESD cable
See
Identifying cables to use with the
on page 31.
4.
Unpack the equipment.
Observe ESD precautions when you
unpack the equipment. See
on page 14.
5.
Verify the contents of the shipped
package.
See
on page 20 for
a description of the components that are
provided with the switch. If any
components are missing, contact
Extreme Networks support.
6.
Make sure that the power cord has
the correct country-specific
termination.
See
on
page 18.
7.
Prepare the equipment rack
Prepare the equipment rack and ensure
that there is enough rack space of 1.75
inches (4.45 centimeters).
Ensure that the rack is bolted to the floor
and braced if necessary.
Ensure that the rack is grounded to the
same grounding electrode used by the
power service in the area. The ground
Table continues…
February 2020
Installing Ethernet Routing Switch 3600 Series