EXHAUSTO 3001414-2000-02-01.fm
5/8
2.2.3
Example 2 – Voltage start signal from timer
(Fig. 5)
The example shows how voltage start signal from the
timer is connected to the EBC 11.
•
Power supply to the control is connected over
terminals 1-3.
•
Connection to the timer and the boiler control.
•
Start signal from the timer (phase) is con-
nected over to terminal 6.
•
Loop terminals 7 and 14.
•
The start signal for the boiler comes on from
terminal 15.
•
Connect neutral from the timer to terminal 4.
Neutral for the boiler can be taken from ter-
minal 5.
•
Loop earth between timer and boiler control.
•
Chimney fan with built-in fail-safe supervision is
connected over terminals 16-21 according to the
installation instructions enclosed with the chim-
ney fan. If an extern pressure switch (PDS) is
used connect the PDS over terminals 16-18 and
the chimney fan over terminals 19-21.
5
Содержание EBC11