E-80-136KTL User Manual
Copyright ©EVOLVE ENERGY GROUP CO.,LTD
- 32 -
Procedure:
Step 1
: Remove the insulation layer with an appropriate length using a wire
stripper shown as figure 5-2
)
Figure 5-2 Grounding connection instruction
(
1
)
Note
:
the length of L2 should 2~3mm higher than L1
Step 2
: Insert the exposed core wires into the OT terminal and crimp them by
using a crimping tool, as shown as figure 5.3. Recommend using OT terminal: OTM6,
Cable:
≥
6mm
2
Figure 5-3 Grounding connection instruction
(
2
)
Note 1:
L3 is the length between the insulation layer of the ground cable and
crimped part. L4 is the distance between the crimped part and core wires protruding
from the crimped part.
Note 2:
The cavity formed after crimping the conductor crimp strip shall wrap the
core wires completely. The core wires shall contact the terminal closely.
Step 3:
Remove the screw from the bottom side of inverter (Shown as figure 5-4),
connect the grounding cable to the grounding point and tighten the grouping screw.
Torque is 6-7N.m