RDT-43-0921
17
®
NORD
fire
|
FDMA-PM
Images are for illustrative purposes
We reserve the right to make changes
Fig. 22 Outside solid ceiling construction- mineral wool- stuffing box and fire protection mastic
EIS 45
Position:
1 Fire damper
2 Solid wall construction
3 Mineral stone wool min.density 150 kg/m³
4 Fire protection mastic min.thickness 1 mm
5 Stone wool with wired mat on one side, density 66 kg/m³
6 Duct
Used materials - example:**
3 Promapyr, Rockwool Steprock HD, Hilti CFS-CT B 1S 140/50
4 Promastop - P, K, Hilti CFS-CT
5 Isover Ultimate Protect Wired MAT 4.0, th. 100 mm ALU1
** The materials for stuffing box, fire protection mastic, lining and insulation materials can be replaced by
another approved fire sealing system with equivalent properties.
The maximum distance of the fire damper from the structure is not limited and according to EN 15882-2,
the required number of suspensions acc. to EN 1366-1:2014 must be used.
The duct at the point of penetration can be anchored to the fire wall construction!
Shown schemes of incorporation and damper are illustrative only!
* Around the perimeter