Final Installation and Power Up
37
Power Up and Test
1:
Turn off all branch circuit breakers and the main circuit breaker (if installed).
2:
Turn on the power source to the panel.
3:
Turn on the main circuit breaker (if installed).
4:
Turn on the breaker in the panel that is feeding the control electronics. This breaker has a blue
handle and is located near the control electronics.
5:
Verify that the control electronics powers up. The display and power LED illuminates.
• If the display does not illuminate, check the incoming power feed and terminations.
6:
Turn on the remaining branch circuit breakers in the panel.
7:
For each load, press the corresponding button on the override panel to verify the load can be
controlled.
If you have any difficulties installing your system, please contact ETC Technical Services at the office
nearest you. See
.
See the
Power Control Processor Configuration Manual
for operation instructions and maintenance
information. Documentation is available for free download on the ETC website
WARNING:
RISK OF DEATH BY ELECTRIC SHOCK! Make sure both front panels and the
door have been installed before turning on the power to the rack.
Install the Door
The door can be installed to open to the
left or to the right.
1:
Orient the door so the hinges are
on the proper side for your
installation.
2:
Attach the door using the eight
screws provided
Door
Front panel