ESS 600-1350 Скачать руководство пользователя страница 10

Upper & Lower Belt Tracker 

10 

14/06/2021 

SECTION 5 - COMMISSIONING 
 

 
Step 1. 

Manually move the guide rollers from side to side to check the system function.

 

Ensure all bolts have been tightened adequately.

 

 

Step 2. Is the belt empty? 

Make sure there are no tools left on the belt 
They may clog up conveyor systems. 
 

Step 3. Start the conveyor. 

 

Follow the established safety rules. 

 

Step 4. Observe the action of the Belt Tracker. 

Check the Belt Tracker action to ensure it is functioning correctly. Allow at least 10 revolutions of 
the belt.

 

If  adjustment  is  required,  turn  off  and  lock  out/tag  out  the  energy  source  to  the  conveyor  and 
conveyor accessories.

 

Check and tighten all fasteners after running the belt.

 

 

Step 5. Demonstrate the system to the Operating Supervisors and Crew. 

Call  the  Supervisors  responsible  for  the  maintenance  and  operation  to  the  site.  Make  a 
short run of the system. Show the operator how to adjust the system. 

 
Step 6. Secure the system for production. 
 

Follow plant procedure to secure the conveyor for production. 

Содержание 600-1350

Страница 1: ...Upper Lower Belt Tracker 1 14 06 2021 Upper Lower Belt Tracker 600 1350 Belt Widths Installation Operations Manual...

Страница 2: ...t QLD 4740 PO Box 5755 Mackay Mail Centre QLD 4741 07 4952 4600 essmac esseng com au MAITLAND Unit 2 Barton Court 6 Johnson Street Maitland NSW 2320 02 4932 3544 essmai esseng com au PERTH 26 Midas Ro...

Страница 3: ...ty by way of consequential loss arising out of defects in the product You are asked to note that ESS offers purchasers a service whereby either a It will install the product and certify the correctnes...

Страница 4: ...ECTION 3 PREPARATION FOR INSTALLATION SECTION 4 INSTALLATION SECTION 5 COMMISSIONING SECTION 6 OPERATOR TRAINING SECTION 7 ROUTINE MAINTENANCE AND SERVICE SECTION 8 TROUBLE SHOOTING SECTION 9 INSTALLA...

Страница 5: ...should servicing or installation of the Belt tracker be carried out whilst the belt is in operation The conveyor must be shut down and locked out before any person enters or reaches into the conveyor...

Страница 6: ...ining idler The upper guide unit is used on the carry side of the belt the lower guide unit is used on the return side A steering roller must be supplied by the client Typically the roller removed fro...

Страница 7: ...enable you to a Verify all required equipment is present b Familiarise yourself with the Belt Tracker assembly c Allow you to plan the installation reducing installation time 3 ASSEMBLE THE FOLLOWING...

Страница 8: ...n place Step 3 Fit the cross section pivot plate into position using the M12 x 210 lg bolt nyloc nut Tighten the nut check that the cross section pivots freely Step 4 Adjust both the rear cross sectio...

Страница 9: ...stance from the guide frame and tighten adjustment screws Step 10 Adjust the guide arms on the upper belt tracker to the belt trough angle Adjust the front cross section to allow the belt to contact a...

Страница 10: ...ker Check the Belt Tracker action to ensure it is functioning correctly Allow at least 10 revolutions of the belt If adjustment is required turn off and lock out tag out the energy source to the conve...

Страница 11: ...instruction with your conveyor system shut down 3 Give a hands on instruction with your conveyor system running 4 All services must be recorded and given to a person of responsibility 5 Encourage the...

Страница 12: ...s will vary considerably from plant to plant Inspection Inspect the condition of the Belt Tracker Check the pivot points and guide rollers for free movement If maintenance is required Step 1 Shut down...

Страница 13: ...e Belt tracker will be mounted PROBLEM Groove worn into the guide roller CAUSE SOLUTION Guide roller bearing may be seizing Replace guide rollers Torque arm Front or Reat pivot points may be seizing C...

Страница 14: ...Revision C 14 SECTION 9 INSTALLATION DRAWINGS...

Страница 15: ...Upper Lower Belt Tracker 15 14 06 2021...

Страница 16: ...Upper Lower Belt Tracker 16 14 06 2021...

Страница 17: ...Upper Lower Belt Tracker 17 14 06 2021 SECTION 10 EXPLODED PARTS DRAWINGS...

Страница 18: ...__________________________ 3 Was work carried out as per procedure and JSA Yes No If No WHY________________________________________________________________________________ ____________________________...

Отзывы: