background image

WARNING
•     This product must be disconnected from the circuit if subjected to any high 

 

voltage or insulation resistance testing. Irreparable damage will occur if this 

 

instruction is not followed 

•   

Recommended routine test procedure in accordance with BS 5266 

•   

Daily check - check that the status GREEN LED indicator is illuminated 

•     Monthly functional test - simulate a mains supply failure for approx. 30 secs by

operation of a key switch or circuit breaker. Ensure normal supply 

 

is restored after test and the indicator status LED is illuminated. 

•     Twice yearly conduct a one hour duration test - simulate a mains supply failure 

breaker. Ensure normal supply is restored after test and the indicator status LED 
is illuminated 

•     Annual full three hour duration test - conduct a three hour continuous 

 

duration test. Simulate a mains supply failure for three hour continuous test by 

r. Ensure normal supply is 

restored after test and the indicator status LED is illuminated 

•     

 

GENERAL

the correct manner when it reaches the end of its life. Check local authorities for 
where facilities exist. Clean with a soft dry cloth only , do not use aggressive cleaning 

GENERAL INSTRUCTIONS
These instructions should be read carefully and retained after installation by the end 
user for future reference and maintenance.  

 

SAFETY
•   

  

or competent person to the current IEE Wiring Regulations 

•  

 Please isolate mains prior to installation/maintenance

•   

  

not exceed the rating of the circuit cable, fuse or circuit breaker

•   

  Please note the IP (Ingress of Protection) rating of this luminaire when deciding 

 

the location for installation

electrician. See overleaf for test record sheet

INSTALLATION

•   

  Provide power to the required point of installation. Suitable IP rated junctions 

boxes should be used where required

•   

with any joists, gas or water pipes or electrical cables

 

•  

  For non-maintained operation please wire up connector block as shown in Fig 3

•  

 For maintained operation (luminaire always on) please see Fig 4

•     For switchable maintained operation   

see Fig 5

•     Connect the battery via the plug and   

socket on the PCB

•     Switch on the power supply and ensure   

the LED indicator is illuminated Green

• Remove two screws   

 

• Pull apart tabs (see Fig 2) to   

gain access to the connections

Fig 1

Fig 2

Fig 3

Fig 4

Fig 5

Insert link 

 

cable

Remove screws

Pull apart tabs

• Switch on the power supply and ensure the LED status indicator is illuminated
green to ensure the battery and supply are functioning.
After 36 hours on continuous charge a mains failure should be simulated to ensure
successful operation.

Отзывы: