9910046 RevG April 2021
PAGE
9
3. Build East Edge Row
S
L
Spacer Stick
S
L
ALERT:
To
ensure
system
alignment, use the Spacer Stick
to align Module Connectors
before securing Rails.
Place East Module Assemblies with the Base Pads
along the East Edge line. The first and last East
Module Assemblies should be placed with the edge
of the Base Pads on the Base Edge line.
Tip
: Raise Tilt Arms after securement of assembly.
3.2
Place a Rail on all
“S”
spacings (module centered).
Rails at row ends should be flush with array edge
when
“S”
spacings permits.
Place a Rail on all
“L”
spacings (between modules) on
top of and overlapping the Rails on the
“S”
spacing.
Install bolt and tighten to
6 ft-lb.
S
L
3.3
Base edge
measured to
Pad edge
Tip
: Base Edge
is in line with
Base Pad
Tip:
“S” spacings are module centered
“L” spacings are between modules.
Tip:
L, S, R and AEBE dimensions
are found in the Racking
Construction Set. See Sheet
Title: Typical Array Dimensions.
Snap East Edge, Array Edge, and Base Edge lines.
Tip:
Snap Array Edge lines on one or both array
edges (row ends) and snap Base Edge line on the
edge where module mounting will begin.
3.1
See Sheet Title Page: Typical
Array Dimensions in the Racking
Construction Set for AEBE
dimension.
Scan here for
rail installation
video
ALERT:
Rail on
“L”
Spacing is ALWAYS on
top of Rail on
“S”
Spacing. This
installation sequence is
critical
to system
performance.
Tip
: Rail has two holes. Consult Sheet
Title: Typical Array Dimensions in the
Racking Construction Set for appropriate
hole use.