LBI-38962
32
5.
A banner is displayed on the Diagnostic
Terminal.
SYSTEM.TXT is parsed a second time.
/cnfg/system.rpt is built with the results.
Phase 1 verifies each command and its
parameters.
Phase 2 verifies that the commands are
valid for the board type and that all
required commands are present.
Phase 3 supplies default values as
necessary.
Phase 4 does a complete check of the
configuration.
Phase 5 builds the internal routing tables.
Board waits for parser to complete.
On configured boards, all small LEDs are
lit.
6.
Application is started on board.
Board reports when it is ready.
Application is started on board.
If no errors, the board number is
redisplayed, otherwise an error code is
displayed.
Board reports when it is ready. If it is a
TSI Master, the DIM Link must be
established.
If the board is a TSI Master, LED 7
cycles on & off every 7 seconds if DIM
Link established.
7.
If all boards have reported that they are
ready, all boards are told to start
accepting data calls.
If after 30 seconds, all boards haven't
reported that they are ready, an error is
displayed on the Diagnostic Terminal and
written into the Activity Log.
Boards starts accepting data calls when
told to.
If board is a TSI Master and DIM Link is
down or goes down, board continually
attempts to reestablish link.