Note: if the base in-feed is in the middle of the run then a 3-way splitter is required (UYCONN as
shown above in hand).
18. Connect all Frame-to-Frame power jumpers. Note: you may have an extra jumper at the end of
a run.
19. If you are transferring power around a 90 degree connection then a special jumper (and splitter
if in middle of Spine Wall) is used to go out the bottom of the panel and up into the next panel.
If you are lucky enough to have a 90 degree connection in front of a power/data opening on the
spine you may utilize the hole in the Beltway to route the power.
20. If you are transferring power in a 120 degree connection than a special jumper and a splitter
(UYCONN) is used to go out the end of the frame and into the next Frame.
Data
21. Pick the appropriate dataplate (provided) and add cabling and punch down (customer
provided).
22. Enwork recommends that data cables be routed alongside power (power is shielded). If you
want to use the chamber below you can feed the data cable through the bottom chamber.
Содержание Grid Frame