Enphase Microinverter Installation
Installing the Enphase Microinverter System involves several key steps. Each step listed here is detailed
in the following pages. Follow the instructions in this section to install Enphase M215 Microinverters.
Step 1
: Register the System
Step 2
: Connect the Envoy
Step 3
: Install the AC Branch Circuit Junction Box
Step 4
: Plan, Cut, and Position the Enphase Engage Cable
Step 5
: Attach the Microinverters to the PV Racking
Step 6
: Ground the Microinverters (if required)
Step 7
: Dress the Enphase Engage Cable
Step 8:
Connect the Microinverters
Step 9
: Terminate the Unused End of the Engage Cable
Step 10
: Connect the Engage Cable to AC Junction Box(es)
Step 11
: Complete the Installation Map
Step 12
: Connect the PV Modules
WARNING
: Always de-energize the AC branch circuit before servicing. Never disconnect
the DC connectors under load. Disconnect DC connections first, and then disconnect AC
connections.
WARNING
: DO NOT connect Enphase Microinverters to the utility grid or energize the
AC circuit(s) until you have completed all of the installation procedures as described in
the following sections.