Page 21
Copyright Enphase Energy Inc. 2011
141-00013 Rev 03b
Step 8 – Verification and Commissioning
Prior to final connection to the utility grid, ensure that
all AC and DC wiring is correct.
a.
Ensure that none of the AC and DC wires are pinched or damaged.
b.
Ensure that all junction boxes are properly closed.
c.
Ensure that all unused connectors are capped.
d.
Ensure that all connectors are properly seated.
e.
Install the microinverters and commission the system as instructed
by the Enphase Microinverter installation and operation manual.
Содержание ET10-208-30
Страница 1: ...Installation Manual Enphase Engage Cable and Accessories ...
Страница 4: ...Page 4 Copyright Enphase Energy Inc 2011 141 00013 Rev 03b ...
Страница 6: ...Page 6 Copyright Enphase Energy Inc 2011 141 00013 Rev 03b ...
Страница 24: ...Page 24 Copyright Enphase Energy Inc 2011 141 00013 Rev 03b ...
Страница 26: ...Page 26 Copyright Enphase Energy Inc 2011 141 00013 Rev 03b Sample Wiring Diagram 208 Vac ...
Страница 27: ......