       Install conduit and field wiring, continued

+

 

DANGER! 

Risk of electric shock. Check that the dedicated circuit 

breaker protecting the branch where the IQ Battery(ies) will be 

connected is turned off before wiring. 

WARNING! 

Risk of equipment damage. The DC switch must be 

OFF before installing, otherwise IQ Battery will try to form a grid. 

D ) 

If installing an IQ Battery 10

, install the inter-unit raceways. The 

left-side and right-side conduit openings are different diameters, so 

you must install the raceway in the proper direction. 

•  Face the fronts of the batteries, 

and insert the raceway through 

the right-hand unit’s left-side 

conduit opening from within 

the field wiring compartment, 

with the arm of the raceway 

pointing up. 

•  Push the raceway through the right-hand unit’s left-side conduit 

opening and into the left-side unit’s right-side conduit, opening until the 

two snap features on the raceway engage the left-side unit’s enclosure. 

•  Once fully inserted, rotate the “arm” toward you until it stops. 

• 

The left-side conduit opening of each battery unit has a flat surface, 

without additional features. The larger seal (green) on the raceway 

mates with this opening. The right-side conduit opening has a 

groove around the hole to fit the O-ring (red) of the raceway. Make 

sure that the O-ring is captured in the groove between the IQ Battery 

enclosure and the raceway flange adjacent to the O-ring. 

E )  Using the conductors and suitable conduits, connect the AC dis-

connect and the first adjacent IQ Battery. Use the conduit openings 

provided to connect the conduit and pass the wires through them. 

Note that if an Enphase IQ System Controller is in line-of-sight, the 

breaker can service as a disconnect.

 

WARNING! 

Risk of equipment damage. Do not modify or rewire 

the pre-installed wiring or bonding connections in the field wiring 

compartment. 

WARNING! 

Risk of equipment damage. Always connect to two 

Lines (active) and one ground. 

F )  Connect each wire in the field wiring compartment to its correspond

-

ing conductor (Lines and Ground). Each terminal accepts two 14-8 

AWG conductors (11mm/7/16 inch strip length). Tighten to 14 lb-in.

G ) 

If installing an IQ Battery 10

, route the wires from the first IQ Battery 

to the adjacent  IQ Battery through the inter-unit raceway. There are 

two positions for each line and for ground in the terminal block to 

allow for daisy-chaining.

WARNING! 

Risk of equipment damage. Do not daisy chain more 

than six total IQ Battery 3 or two IQ Battery 10 on a single branch 

circuit. 

H )  After all wires in the field wiring compartment are connected and 

secured, check that there are no exposed conductors. 

I )  If connecting additional IQ Batteries, use another conduit and another 

set of wires to connect between field wiring compartments.

J )  Gently arrange all the wires and connectors inside the field wiring 

compartment.

6

K )  Plug any unused conduit openings before proceeding.

L )  Replace the field wiring compartment cover. Use a cross-head 

screw driver to tighten the cover screws to 2.3Nn (20.3 Ib-in).

WARNING!

 Risk of equipment damage. Ensure that no wires are 

pinched before replacing the cover.

DANGER!

 Risk of electric shock. The system is not ready to 

be energized! Do not close the circuit breaker or turn on the DC 

switch. 

Inter-unit

 

raceway

Correctly installed 

inter-unit raceway

Grommet to be installed on the left 

side or right side when the hole in the 

left side or right side is not used for 

cable routing.

(To be used in IQ Battery 3 when no 

conduit is used with the hole).

(To be used in Right most Base unit in 

IQ Battery 10 when no conduit is used 

with the hole).

       Dismounting of IQ Battery 3 Cover

A) Remove the conduit covers from either sides of the IQ Battery cover

B) Lift up the ring of the quarter turn screw.

C) Turn the ring in the anticlockwise direction to unlock the screw.

D) After unlocking, hold the ring of the screw and lift the top cover
    up slightly and pull it away from the wall in the indicated direction.

E) While pulling out the cover, make sure that the indicated
    snaps at the bottom of the unit are being unlocked. 
F) Simillarly for dismounting the IQ Battery 10 Cover, please follow the 
    instructions from A to E. 

7

Содержание ENCHARGE-3-1P-NA

Страница 1: ...guration for back up of the entire main load panel This configuration supports up to an 80A breaker for the PV circuit and an 80A breaker for battery storage Whole home backup with IQ System Controller as service entrance and PV combiner connected to main load panel This is the preferred configuration when you back up the entire main load panel and the size of the PV combiner circuit is more than ...

Страница 2: ...t screwdriver socket wrench torque wrench level wire stripper and stud finder if installing on studs Fasteners for wall mount bracket Slots are 6 8mm 0 27 Check with a structural engineer and local standards for requirements Single wide bracket Three 1 4 lag bolts or screws 7 6 cm 3 inches long depending on attachment wall Triple wide bracket Nine 1 4 lag bolts or screws 7 6 cm 3 inches long depen...

Страница 3: ...ction circuit The subpanel could be a small two circuit box with circuit breakers The circuit breakers in the box would have to be suitable for back feeding per NEC 408 36 D Select the right size subpanel and breakers based on the number of IQ Battery units being installed Up to four IQ Battery 10s or twelve IQ Battery 3s can be safely connected to 80A load center To do this you must purchase an o...

Страница 4: ... mounting holes on the left and right align with the adjacent studs B Use a level to keep the bottom of the wall mount bracket level C Use 1 4 screws or masonry attachments for masonry to attach the bracket using one screw and washer for each slot 6 8mm 0 27 Use screws in each section of the mounting bracket to support the three IQ Battery units There is an array of slots so that you can choose th...

Страница 5: ...J Use a Phillips screw driver to loosen the screws securing the field wiring compartment cover and remove the cover Keep the cover and screws handy as you will need them later K Attach the battery to the mounting bracket aligning the screw hole at the top of the battery with the screw hole at the top of the bracket L To record the installation of each IQ Battery base unit scan the serial number la...

Страница 6: ...to its correspond ing conductor Lines and Ground Each terminal accepts two 14 8 AWG conductors 11mm 7 16 inch strip length Tighten to 14 lb in G If installing an IQ Battery 10 route the wires from the first IQ Battery to the adjacent IQ Battery through the inter unit raceway There are two positions for each line and for ground in the terminal block to allow for daisy chaining WARNING Risk of equip...

Страница 7: ...crews to attach the cover to the batteries Tighten the screws as needed 8 IQ Battery 10 without cover A Use the Enphase Installer App to commission the IQ Battery ies Once connected to the IQ Gateway refer to the Enphase Installer App help topics for more information B After the IQ Gateway has detected the IQ Battery ies the IQ Battery LEDs operate as described in the following section CONFIGURE a...

Страница 8: ... the IQ Battery ies in storage ensure that AC power is not present and that the DC switch is in the Locked position While in storage damage to the battery can occur from over discharge If the battery state of charge falls to 0 the IQ Battery ies can be damaged or destroyed Because of this the IQ Battery ies must only be stored for a limited amount of time The IQ Battery ies must be installed and e...

Отзывы: