       Mount the Encharge Battery(ies) on the wall

WARNING

: Risk of injury. Take care when lifting.  

Each Encharge battery base unit is heavy (40.5 kg/ 89.3 lbs) and 

requires two persons to lift.

WARNING! 

Risk of injury and equipment damage. Avoid dropping 

the Encharge Battery(ies). Doing so may create a hazard, cause seri-

ous injury, and/or damage the equipment.

WARNING! 

Risk of injury and equipment damage. Protect the 

Encharge Battery(ies) from impact damage and improper use.

WARNING! 

Risk of injury and equipment damage. Do not hold the 

microinverters to lift the unit during installation.

A )  Two person together must lift a single Encharge battery base unit 

from the packaging and place it in upright position (as shown in the 

following image) on a flat surface.

B )  Locate the Encharge lifting points:

C )  The first person lifting must use points 

a

 and 

d

 (as shown) to lift the 

battery. 

D )  The second person lifting must use points 

b

 and 

c

 (as shown) to lift 

the battery.

E )  Together, lift the Encharge battery and bring it to the already 

mounted bracket. 

F )  Hold the Encharge battery straight so that the four bolts on the back 

of the Encharge battery pass through the four key hole slots on the 

corner of the mounting bracket. 

WARNING! 

Risk of injury and equipment damage. Do not release 

the Encharge battery unit until you ensure that the Encharge battery 

unit is fully seated in the wall-mount bracket shelf. 

G )  Once all four battery bolts fully pass through the mounting bracket 

key hole slots, lower the battery down until fully seated within the 

wall-mount bracket and set into the bottoms of the key holes.

H )  Attach the battery to the mounting bracket aligning the screw hole 

at the bottom of the battery with the screw hole at the bottom of the 

bracket. Tighten the bottom screw to 8Nm (70.8 lb-in). 

I )  To record the installation of each Encharge battery base unit, scan 

the serial number label using Enphase Installer Toolkit™ and your 

mobile device.

5

Bottom screw hole

DC Switch

d

c

a

b

       Prepare for field wiring

DANGER!

 Risk of electric shock. The DC switch must be in the 

Locked position before performing this step.

A )  Drill the left wall of field wiring compartment to accommodate the conduit.
B )  Connect field wiring to the top three terminal blocks. 

C )  Size the conductors (Lines and Ground) to account for voltage rise and 

to conform to the tables below. Design for a voltage rise total of less 

than 2%. Encharge can use any circuit breaker size between 10 A and 

40 A. Breaker rating and wire size are installation dependent. 

Number of 

 

Encharge E3T/E10T units

Current (A)

Minimum wire 

size (AWG)

Breaker 

rating (A)

1*E3T

5.3

14

10

2*E3T

10.7

14

15

3*E3T or 1*E10T

16.0

12

20

4*E3T or (1*E10T + 1*E3T)

21.3

10

30

5*E3T or (1*E10T + 2*E3T)

27.7

8

35

6*E3T or 2*E10T or 

(1*E10T + 3*E3T)

32.0

8

40

       *E3T refers to Encharge 3T

       *E10T refers to Encharge 10T

In all cases in the table, it is possible to always use larger conductors 

and a breaker sized for that conductor or smaller. For Example in row 3, 

with 3*E3T or 1*E10T, it is possible to use:

             a) 12 AWG wire with 20 A breaker, or 

             b) 10 AWG wire with 20 A or 30 A breaker, or

             c)  8 AWG wire with 30, 35, or 40 A breaker

+

 

DANGER! 

Risk of electric shock. Check that the dedicated circuit 

breaker protecting the branch where the Encharge Battery(ies) will be 

connected is turned off before wiring. 

WARNING! 

Risk of equipment damage. The DC switch must be 

OFF before installing, otherwise Encharge will try to form a grid. 

6

Location for 

conduit cut out

Finished Goods 

Serial numbers 

labels

       Install conduit and field wiring

DANGER!

 Risk of electric shock. The DC switch must be in the 

locked position before performing this step.

A ) 

If installing an Encharge 10T

, install the interconnect cable assembly. 

•  Face the front of the batteries, and insert the interconnect cable 

assembly through the front cable slot from within the field wiring 

compartment, with the arm of the interconnect cable pointing up, 

making a “U” shape.

B )  Using the conductors and suitable conduits, connect the AC disconnect 

and the first adjacent Encharge Battery. Use the conduit openings 

provided to connect the conduit and pass the wires through them. Note 

that if an Enphase Enpower is in line-of-sight, the breaker can service 

as a disconnect.

 

WARNING! 

Risk of equipment damage. Do not modify or rewire the 

pre-installed wiring or bonding connections in the field wiring compart

-

ment. 

WARNING! 

Risk of equipment damage. Always connect to two 

Lines (active) and one ground. 

(CONTINUED ON NEXT PAGE)

7

PCBA Serial 

Numbers

Содержание ENCHARGE-10T-1P-NA

Страница 1: ...que installation scenarios are shown Whole home backup with Enpower as service entrance and PV combiner connected to Enpower This is the preferred configuration for back up of the entire main load panel This configuration supports up to an 80A breaker for the PV circuit and an 80A breaker for battery storage Whole home backup with Enpower as service entrance and PV combiner connected to main load ...

Страница 2: ...ch torque wrench level wire stripper and stud finder if installing on studs Fasteners for wall mount bracket Slots are 9 2mm 0 36 Check with a structural engineer and local standards for requirements Single width bracket for Encharge 3T A minimum of three 20 5 16 lag bolts or screws 7 6 cm 3 inches long depending on attachment wall Triple width bracket for Encharge 10T A minimum of nine 20 5 16 la...

Страница 3: ...ts according to local codes standards and other applicable requirements Enpower supports up to a maximum of 80 A breaker for Encharge connection circuit The subpanel could be a small two circuit box with circuit breakers The circuit breakers in the box would have to be suitable for back feeding per NEC 408 36 D Select the right size subpanel and breakers based on the number of Encharge units being...

Страница 4: ...9 2mm 0 36 Use with a minimum of nine screws in each mounting bracket to support the three Encharge battery units There is an array of slots so that you can choose those that allow you to mount the bracket on studs Tighten all screws to manufacturer s specified torque values D Verify that the wall mount bracket is solidly attached to the wall WARNING Risk of injury and equipment damage Do not moun...

Страница 5: ... compartment to accommodate the conduit B Connect field wiring to the top three terminal blocks C Size the conductors Lines and Ground to account for voltage rise and to conform to the tables below Design for a voltage rise total of less than 2 Encharge can use any circuit breaker size between 10 A and 40 A Breaker rating and wire size are installation dependent Number of Encharge E3T E10T units C...

Страница 6: ...charge 3T Cover and energize the system WARNING Before energizing make sure that ALL Encharge Bat teries in the system are properly installed and conductors terminated WARNING Risk of equipment damage Ensure that no wires are pinched before replacing the cover NOTE Check the box for updates on cover installation instructions IMPORTANT The section 8 and 9 will depict instructions for assemby and di...

Страница 7: ...harge cover B Using the hand access slots pull the top plastic grill slightly in the direction shown below in order to unlock the top plastic cover from the ribs highlighted in red Encharge 10T Cover Encharge 3T Cover Encharge 3T Cover Hand Access slots NOTE Only for reference purpose the Enchage 10T Cover image is shown above for locking Cover and energize the system continued B Turn ON the AC po...

Страница 8: ... is restored it automatically starts up again C If you do not see Encharge information in Enlighten check that the IQ Envoy and the Internet connection are working If the issue persists contact Enphase Customer Support at enphase com en us support contact A Use the Enphase Installer Toolkit to commission the Encharge Battery ies Once connected to the IQ Envoy refer to the Installer Toolkit help to...

Страница 9: ... the Encharge Battery ies in storage ensure that AC power is not present and that the DC switch is in the Locked position While in storage damage to the battery can occur from over discharge If the battery state of charge falls to 0 the Encharge Battery ies can be damaged or destroyed Because of this the Encharge Battery ies must only be stored for a limited amount of time The Encharge Battery ies...

Отзывы: