7.0 SYSTEM
INSTALLATION
EnerSys flooded batteries are installed on racks that differ in type, size, seismic rating, and
configuration. Refer to the
RACK ASSEMBLY DRAWING
and instructions included with the rack
shipment for the details of your installation.
7.1 System
Layout
Lay out the battery system before installation. Consult Section 5.0 for installation considerations.
1.
Locate the system position in the area designated as determined in Section 5.0.
2.
Mark the floor with system outline dimensions.
3.
Using the
RACK ASSEMBLY DRAWING
and instructions and rack components, locate the
position of the floor anchors.
Floor anchors are the responsibility of the owner. Follow the installation instructions of the
anchor manufacturer.
The floor must be level. Shimming up to 1/4 inch (6 mm) may be required to have the
Battery System fully level.
NOTE:
The floor must be capable of supporting the weight of the Battery.
The Battery Rack must be securely anchored to the floor. Anchoring should meet all local,
state and/or federal codes and such compliance is the responsibility of the owner. Floor
anchoring and its design are the responsibility of the owner. Ensure seismic requirements
are considered.
4.
Batteries should be kept in the original shipping containers until installed. However, if you
must remove the batteries before installation, see the procedures in Section 6.3, “Cell/Jar
Handling.”