Overfill Prevention System SOP300
Commissioning
Hauser
27
8
Commissioning
8.1
Function check
Before commissioning the Overfill Prevention System:
Make sure that the post-installation and post-connection checks have been performed:
– "Post-installation" checklist,
Section 5.3
– "Post-connection" checklist,
Section 6.2
8.2
Switching on the Overfill Prevention System
Prerequisites:
• The system has been installed correctly.
• The electrical connection has been established correctly.
8.2.1
Switching on the Overfill Prevention System with an optional UPS
L
DANGER
Damaged battery connection cable!
Risk of fatal injury from electric shock.
‣
When closing the front cover for the battery, do not pinch or damage the insulation of the
battery connection cable.
In the case of a non-redundant power supply
1. Insert the fuse of the UPS battery → 27. See wiring diagram "+PS1-14G3".
2. Switch on the circuit breaker. See wiring diagram "+PS1-11F1".
In the case of a redundant power supply
1. Insert the fuse of the UPS battery → 27. See wiring diagram "+PS1-14G3".
2. Switch on the first circuit breaker. See wiring diagram "+PS1-11F1".
3. Switch on the second circuit breaker. See wiring diagram "+PS1-12F1".
Inserting the fuse of the UPS battery (+PS1-14G3)
1. Press the two locking lugs at the top of the battery housing simultaneously and swivel
the front cover down.
2. Insert the fuse into the fuse holder.
3. Close the front cover. The locking lugs must snap into the attachment on the housing
top.
8.2.2
Switching on the Overfill Prevention System without an optional UPS
In the case of a non-redundant power supply
‣
Switch on the circuit breaker. See wiring diagram "+PS1-11F1".