Commissioning (installation and configuration)
Hauser
13
‣
Before starting work: personnel must read and understand the instructions in the manual
and supplementary documentation as well as the certificates (depending on the
application).
‣
Personnel must follow instructions and comply with general policies.
The operating personnel must fulfill the following requirements:
‣
Personnel are instructed and authorized according to the requirements of the task by the
facility's owner-operator.
‣
Personnel follow the instructions in this manual.
4.2
Installation
The mounting and wiring of the device and the permitted orientations are described in the
Operating Instructions pertaining to the device.
4.3
Commissioning
The device is commissioned using the Commissioning Wizard. The commissioning procedure
is described in the Operating Instructions pertaining to the device.
Prior to operating the device in a safety instrumented system, verification must be performed
by carrying out a test sequence as described in
Section 6 Proof testing
.
4.4
Operation
The operation of the device is described in the Operating Instructions pertaining to the device.
4.5
Parameter configuration for safety-related applications
The device settings may not be changed if SIL operation is in progress.
NOTICE
The protective function can be impaired
After commissioning the measuring system, changes to the settings can impact the protective
function
‣
After changing the settings, perform a proof test to ensure that the safety function is
working correctly