BUILT-IN FIREPLACE INSTALLATION
Built-In Fireplace Installation
Built-in installation of this fireplace involves installing the fire
-
place into a framed-in enclosure. This makes the front of the fire
-
place flush with a wall. If installing a mantel above the fireplace,
you must follow the clearances shown in Figure 9. Follow the
instructions below to install the fireplace in this manner.
Frame in rough opening. Use dimensions show in Figure 1 for a
conventional rough opening. Use dimensions shown in Figure 2
for corner rough opening. Be sure to provide gas line for fireplace
and electrical power for optional blower assembly.
1. Attach two (2) nailing flanges to firebox sides with two (2) 10
x 1/2" screws for each nailing flange.
2. Gas line connections must be made at this time. When fac-
ing the appliance, the gas supply will enter on the right-hand
side. See "Gas Supply" page 11.
3. Insert fireplace into enclosure.
4. Attach nailing flanges to framing with a screw or nail.
5. Finished wall surface will be flush to the leading edge of fire
-
place top and sides.
6. Installation of built-in fireplace is completed.
Figure 2
Figure 3
Figure 1
Rough Opening for Installing in Wall
Rough Opening for Installing in Corner