Installing the Electronics Control Unit
March 2017
Installing the Electronics Control Unit
If the installation is adversely affected by the operation of nearby equipment, then
re-routing the cables to these instructions should improve performance:
Avoid bundling the cables together.
Ensure that cables run against earthed (grounded) metalwork, where possible.
Use shielded (screened) cables for all connections, making sure a good annular
(ring shaped) contact is made with a good quality RF cable gland.
Do not run cables over the PCB, where possible.
Figure 3-16. Connector Locations on Front Panel PCB
A. Connector for plugging in fault and status outputs, and status reset input cable.
B. Connector for plugging in power supply connection cable.
C. Grounding (earthing) point.
D. Connector for plugging in electrode cable.
Hydratect Channel 2
Hydratect Channel 1
PL404
PL204
PL101
PL201
PL406
PL206
PL403
PL203
PL405
PL205
A
D
B
C
Содержание Mobrey Hydratect 2462
Страница 1: ...Reference Manual 24625020 Rev AA March 2017 Mobrey Hydratect 2462 Steam Water Detection System ...
Страница 2: ......
Страница 16: ...10 Reference Manual 24625020 Rev AA Introduction March 2017 Introduction ...
Страница 26: ...20 Reference Manual 24625020 Rev AA Installing the electrodes March 2017 Installing the electrodes ...
Страница 52: ...46 Reference Manual 24625020 Rev AA System Testing March 2017 System Testing ...
Страница 62: ...56 Reference Manual 24625020 Rev AA Electronics Servicing March 2017 Electronics Servicing ...
Страница 65: ......