52
Outdoor Installation
Base/Pedestal Plan
Cutouts in Base/Pedestal for
AEROTOP T07-T35
The base or pedestal should project
beyond each side of the heat pump for
about 50 mm and be approx. 300 mm
high (adjust to local snow conditions
as needed). A conduit (NW 250) must
be installed between building and heat
pump for the installation lines (electrical,
hydraulic, and condensate).
Setup Base/Pedestal
AEROTOP T
a1
c1
h1
T07
1095 750 300
T10
1195 850 300
T12, T14, T16
1295 850 300
T20, T26
1295 980 300
T32, T35
1395 1100 300
Min. 800mm
min. 500 mm
c1
a1
242 mm
242 mm
min. 50 mm
Ø 175
Min. 800mm
min. 500
AEROTO T07-T16
AEROTO T20 - T35
Ø 175 mm
Содержание AEROTOP T Series
Страница 87: ...Notes 87...