Follow these procedures to ensure extended safety and performance.
C-1
Appendix C: Service and Maintenance
Ecolibrium recommends
periodic re-inspection of
the installation for loose
components, loose
fasteners, and any
corrosion, such that if
found, the affected
components are to be
immediately replaced.
If module removal is
required, it is the
installers responsibility
to ensure the ground
path is maintained
when the module is
removed. One of two
bonding options may be
utilized:
Option 1
(for use on a
single row array):
A. Install an approved
ground lug on adjacent
modules.
l
Wiley WEEB-LUG-6.7
l
Ilsco Lay-in Lug GBL-
4DBT
l
Burndy CL50-1TN
Other UL 2703 listed,
outdoor rated (by
others) ground lugs may
also be suitable for this
system if approved by
the AHJ (Authority
Having Jurisdiction).
Install ground lug on
both of the modules
adjacent to the module
to be removed. Use the
grounding hole on the
frame of the module.
See section 10 for
additional ground lug
information.
B. Connect a Bonding
Jumper.
Lay a bare #6 CU
conductor (by others)
into the two lay in lugs
connected to the
adjacent modules.
Option 2
(for use on a
multiple row array):
Install a row to row
bonding on either end
of the row.
#6 CU Conductor
#6 CU Conductor
Underside of
Module
l
Install approved grounding lug per
lug manufacturers instructions. See
Section 10.
l
Deburr any field-drilled holes.
l
Wiley WEEB Lugs are “single use
only“.
Ground Lug
Ground Lug
EcoX Gen2 Installation Guide, Rev 1.11
Содержание EcoX
Страница 1: ...EcoX Gen2 Installation Guide Rev 1 11 Installation Guide Gen2 ...
Страница 31: ...EcoX Gen2 Installation Guide Rev 1 11 26 of 31 11 Grounding and Bonding cont ...
Страница 32: ...EcoX Gen2 Installation Guide Rev 1 11 27 of 31 11 Grounding and Bonding cont ...
Страница 33: ...EcoX Gen2 Installation Guide Rev 1 11 28 of 31 11 Grounding and Bonding cont ...