8
Rinse Thermistor/Injection Installation
The rinse aid injection point must be installed downstream of the vacuum
breaker, and a minimum of 6” (15.2 cm) vertically below the vacuum breaker.
Note: Some international installations require this distance to be 30 cm (11.8”).
The enclosure must be mounted so that the top of the rinse dispenser pump is
below the injection point.
NOTICE
Install fittings using Teflon tape or pipe sealant to prevent leaks
1. Identify point at which rinse additive will be injected into final rinse line.
a. If ports are available on the machine rinse line for separate
installations of the rinse injection line and the thermistor, use the
supplied 1/8” FNPT x 1/8” MNPT brass bushing ONLY.
-OR-
b. If the thermistor and rinse line must be installed in the same port, use
the supplied 1/8” brass street tee and follow the diagram below
Note: The Rinse Additive tube must be installed 1.5” (3.0 cm) past the end of
the brass tee fitting for accurate rinse temperature measurement.
2. Assemble the Visual Flow Indicator (required for NSF listing) on the
outlet side of the rinse dispensing pump by inserting the 1/8” tube fully
into one of the two 1” sections of 1/4” OD x 1/8” ID PVC tubing provided
[See Figure 4.7]
3. Install the check valve between the visual flow indicator and the rinse aid
injection point.
1.500
6”
Figure 4.6
Figure 4.7
Figure 4.8