Ecodense WT-S DHW 45 H Скачать руководство пользователя страница 10

 

 

04.12.2020 Rev. 00 

 
 

5.

 

WATER QUALITY 

 

1.

 

Before connection of condensing boilers any dirt and residue in circuit must be cleaned. 

 

2.

 

Water Hardness and pH measurements should be made by the authorized or central service in the 

field where the boiler will be commissioned before the commissioning, and it should be decided 
whether the water can be used in the boiler water installation. 
 

3.

 

Refined water must be used while adding water to heating circuit due to any loss in closed circuit.  

 

4.

 

Permitted water hardness for the water used in water circuit must comply with  French or German 

(VDI  2035)  hardness  degree  standards.  The  lime  dissolved  in  water,  settles  on  hot  surfaces  and 
forms  an  insulation  layer  when  water  temperature  rises.  This  prevents  heat  transfer  and  high 
temperature  might  damage  the  heat  exchanger.  If  boiler  water  cycles  through  water  circuit,  all 
circuit water must meet above requirements. If a plate heat exchanger separates boiler water and 
heating  circuit  water,  only  the  water  between  boiler  and  heat  exchanger  must  meet  these 
requirements. 

 
In order to prevent sedimentation, properties of the water to be used or to be reinforced in the water line 
should not exceed the following table values according to below mentioned capacities. 

 

Boiler Type

 

Capacity

 

(Total Hardness) 

 

ppm

 

(°F) French

 

VDI German

 

Single Boiler

 

0-50 kW

 

250

 

<

 

25

 

<

 

14

 

Single Boiler

 

50-200 kW

 

110

 

<

 

11

 

<

 

6,16

 

 

*Volume  to  capacity  ratio  of  water  in  circuit  must  be  higher  than  20  I/kW.  Total  volume  of  first  filled 
water and additional water must be less than volume of system.  

 

5.

 

The customer or contract company  should analyze  the water to be used in the water line by an 

accredited organization prior to commissioning and a water quality report should provided 
containing Minimum Hardness, pH and conductivity values, total dissolved solid values  .

 

 

6.

 

pH value of unrefined water must be 7<pH<9. This pH value can be achieved after filling the 

circuit  with  main  circuit  water  with  pH  value  of  7  and  air  separation.  pH  value  of  refined 
water must be between 7-8,5 pH. 

 

7.

 

In  new  building  installations,  periodic  preventive  maintenance  must  be  carried  out  by  using 

organic solutions with a chemical pH effect [neutral]. 

 

8.

 

Prior to commissioning of condensing boilers in old building water installations, a suitable type of 

organic solution with a pH value (acidic) between 4 and 6 should be washed.

 

 

9.

 

The  boiler  water  pipeline  and  heat  exchanger  should  be  treated  with  a  suitable  type  of  organic 

solution over a period of 6 to 12 months to prevent calcification and deposits that may occur over 
time in the installation.

 

 

10.

 

If the water quality is outside the value ranges given above, it is mandatory to use a water 

softening filter or electrolytic limescale reducer in the system for water installations. 

 

Содержание WT-S DHW 45 H

Страница 1: ...NSTALLATION OPERATING AND MAINTENANCE MANUAL ECODENSE WT S DHW 45 L ECODENSE WT S DHW 45 H ECODENSE WT S DHW 45 XH ECODENSE WT S DHW 55 L ECODENSE WT S DHW 55 H ECODENSE WT S DHW 55 XH ECODENSE WT S D...

Страница 2: ...y warnings thoroughly before the use of the device in order to ensure safe cost effective and environmental friendly use If you encounter any issue that is not explained clearly in this manual or you...

Страница 3: ...12 8 INSTALLATION 13 8 1 General Controls 13 8 2 Assembly of Condensing Fluid Drain 14 9 ECODENSE CONTROL INSTRUCTIONS BEFORE START UP 15 9 1 Control Panel Description 16 9 2 Display Description 16 9...

Страница 4: ...riptions Important information and useful hints Warning of danger to life or property Warning of electrical voltage Product handling information GAZ HATTINI TEM ZLEY N Z CLEAN GAS LINE Clean the gas l...

Страница 5: ...ty elements should be carried out only by the manufacturing company The device should never be used by children mentally handicapped and inexperienced persons Children must not be allowed to play with...

Страница 6: ...en to the atmosphere and Bird cage should be installed in order to prevent any Bird foreign body entrance a The build up of toxic explosive gas mixtures in the boiler room b Combustion with insufficie...

Страница 7: ...es Any damage that may occur during transportation or storage of the product Not preserving the product in its original packaging until the installation stage Incorrect and poor electrical connections...

Страница 8: ...04 12 2020 Rev 00 7 3 CONDENSING BOILER GAS FLUE GAS AND HEATING WATER SCHEMA WT S DHW SERIES...

Страница 9: ...04 12 2020 Rev 00 8 4 CIRCUIT SCHEMES WT S DHW SERIES...

Страница 10: ...rdness ppm F French VDI German Single Boiler 0 50 kW 250 25 14 Single Boiler 50 200 kW 110 11 6 16 Volume to capacity ratio of water in circuit must be higher than 20 I kW Total volume of first filled...

Страница 11: ...04 12 2020 Rev 00 10 6 TECHNICAL DATA 6 1 Capacity Table...

Страница 12: ...according to the product standards at the time of expansion of the smoke release system when the condensing boiler operates at the maximum heating power MODEL W mm H mm L mm Boyler Tank Volume L WT S...

Страница 13: ...12 7 CONDENSING BO LER HANDLING INFORMATION Prevent strong impacts on top of the product and vibration while handling the product Do not leave the product in wet environment Device must be shipped in...

Страница 14: ...connections are made with pipes confirming to the standards and that there is no leakage on these connections Ensure that the electric connections are proper Clean the inside of fuel line thoroughly...

Страница 15: ...nal effect like frost etc Drain parts must be plastic 3 Boiler condensing outlet must be at least 13 mm Condensing drain must not be changed or clogged after assembly Clogging of condensing drain caus...

Страница 16: ...complies with boiler operation instructions In situations where gas pressure is higher than required pressure a regulator must be used 9 Ensure that sensors on boiler feed and circuit outgoing return...

Страница 17: ...CH setpoint adjustment K6 DHW setpoint adjustment K3 OFF Info mode selection K7 DHW setpoint adjustment K4 RESET mode 9 2 Display Description S1 DHW mode S9 Solar mode S2 Reset request S10 S17 Water p...

Страница 18: ...g boiler is worked on DHW mode and tap symbol will be flashing when condensing boiler works at DHW mode Because of the DHW priority even if the appliance is operating at CH condensing boiler will swit...

Страница 19: ...04 12 2020 Rev 00 18 10 ELECTRICAL DIAGRAM AND RELATED CONNECTIONS WT S DHW...

Страница 20: ...04 12 2020 Rev 00 19...

Страница 21: ...04 12 2020 Rev 00 20...

Страница 22: ...the connections of the related terminals in the panel box as shown in the illustration below Closure of Room Thermostat contact generates a heat demand in CH mode If the room thermostat is not connec...

Страница 23: ...capacities again and adjust combustion parameters precisely by following above steps After adjustment of parameters are finished close all measurement points as they will be leak proof Flue gas emiss...

Страница 24: ...bolts of the boiler Tighten loose bolts After starting the condensing boiler and making required adjustments perform flue gas emission measurement and check if there is an ideal combustion 13 2 Seaso...

Страница 25: ...de expected bounds meaning a problem on electronic components E09 Valve feedback error The valve feedback doesn t respect controller commands E12 EEPROM integrity lockout The EEPROM check fails The da...

Страница 26: ...Shaky activation of burner Gas pressure Combustion parameters Check the gas pressure and combustion parameters No combustion after ignition Electrode Ionization Check the position state of the electro...

Страница 27: ...YE Tel 90 216 442 93 00 Fax 90 216 370 45 03 Factory Contact Details T rkg c OSB B lent Ecevit Bulvar No 11 ORLU TEK RDA T RK YE Tel 90 282 685 44 80 81 Fax 90 282 685 42 09 You can also reach us thro...

Страница 28: ...04 12 2020 Rev 00 27 17 NOTES Please record and forward your measurements and observations to us www ecodense com...