Eaton Static Transfer Switch 2000A 3-Pole Installation and Operation Manual 164001127—Rev 01
23
C
Chhaapptteerr 44 S
Syysstteem
m U
Unnppaacckk aanndd IInnssppeeccttiioonn
!
IMPORTANT
Read this entire Installation and Operation manual before installing and operating the unit.
Upon receipt of the STS, the Installer should perform the following steps to assure a high quality installation.
44..11
EExxtteerrnnaall IInnssppeeccttiioonnss
1.
While the STS is still on the truck, inspect the equipment and shipping skids for any signs of damage or
mishandling. If the system shows any damage, note it on the freight bill and file a damage claim with the
carrier within 24 hours. Please contact Eaton Service (1-800-843-9433) if damage has occurred. Do not
attempt to install the system if damage is apparent.
2.
Locate the bag containing the keys for the front doors, which will be attached to the cabinet.
3.
Verify that all units have been received.
4.
Compare the contents of the shipment with the bill of lading. Report any missing items to the carrier and
Eaton PDI immediately.
5.
If you ordered spare parts, verify that they arrived.
6.
If the unit is to be stored before installation, it should be stored in a dry environment within storage
temperatures specified in
. Use the original packing materials or other
suitable means to keep the unit clean.
44..22
U
Unnllooaaddiinngg,, U
Unnppaacckkiinngg,, aanndd H
Haannddlliinngg
You should unpack your Eaton PDI product with the same care used in packing the product for safe and
efficient delivery to your facility.
•
Use the shipping skid provided to move the system as close as possible to the final installation position. A
forklift or pallet jack can be used to move the skid. Do not exceed a 10- degree tilt if moving with a forklift.
Tipping the unit can cause it to fall which can cause damage or injury to personnel.
•
Exercise care when handling STS system cabinets to avoid equipment damage or injury to personnel.
•
Before moving the unit, check the unit size and weight in
.
•
Plan your route for moving the equipment. Ensure that all passages are large enough to accommodate the
unit and support the weight. Check for any non-negotiable corners or offsets in hallways.
•
To remove the unit from the skids, carefully cut the bands holding the unit or unit modules to the pallets.
Use cautions as bands are under tension and can cause personal injury. When opening the shipping
package, use care not to puncture the packaging with sharp objects. Remove all plastic wrapping and
packing material from the unit.
•
Lift the units off the skids with a forklift capable of handling the weight of the unit. Lift the STS unit from
the front between the shipping skids. Ensure that the unit is located on a level floor with room to
maneuver around it.
44..33
IInntteerrnnaall IInnssppeeccttiioonnss
Execute the following inspections as soon as possible upon arrival of your Eaton PDI equipment:
1.
Open the front door and check the nameplate on the cabinets to verify that the model numbers correspond
with the ones specified on the bill. Record the model and serial numbers in your Installation and Operation
manual or in other accessible locations for service reference.
Содержание STS 2000A
Страница 1: ...p n 164001127 Revision 01 Installation and Operation Manual Eaton Static Transfer Switch 2000A 3 Pole...
Страница 8: ......
Страница 16: ...xvi Eaton Static Transfer Switch 2000A 3 Pole Installation and Operation Manual 164001127 Rev 01 List of Tables...
Страница 32: ...16 Eaton Static Transfer Switch 2000A 3 Pole Installation and Operation Manual 164001127 Rev 01 Safety...
Страница 98: ...82 Eaton Static Transfer Switch 2000A 3 Pole Installation and Operation Manual 164001127 Rev 01 Troubleshooting...
Страница 120: ...16400112701 164001127 01...