New generation IZM97, 99 low voltage air circuit breaker instruction manual
MN013010EN February 2020 www.eaton.com.cn
Section 4: Accessory devices
Cable
Bracket screw (K)
Hexagonal
bracket (H)
Interlocking
adapter (D)
Connect screw (J)
Castell key lock
mounting panel (C)
Orientation (the
key should be
inserted into
cylinder lock slot)
Cylinder lock slot
Press with
one finger –
adjust later
Castell key lock (B)
(not supplied)
Note the direction
Clamping
bracket
(E)
Torsion
spring (F)
Spring pin (G)
Side view
Tension spring (I)
Mounting
screw (O)
Figure 6. Step 6
Figure 7. Step 7
Figure 5. Step 5
Step 5: Remove the existing screw from the back of the cyl-
inder lock (B), and fix the cylinder lock to the mounting panel
(C) using a screw. Ensure the key mounting orientation in
this step and subsequent steps. Pay attention to the cylindri-
cal lock slot orientation when mounted to a lock panel.
Step 6: Install the interlocking cable (L), hexagonal bracket
(H), and interlocking adapter (D). Connect and fasten them
using the bracket screws (K) and connect screws (J).
Step 7: Install the kits assembled in Step 5 to the kits
assembled in Step 6. Make sure that the axis orientation of
the key and the hexagonal cylindrical bracket are consistent.
Step 8: Install the torsion spring (F) and clamping bracket (E)
on the kits assembled in Step 7. Fasten it using the spring
pin (G). Make sure that the free bending direction of the
spring is shown in the side view below.
Step 9: Install the kits assembled in Step 8 to the circuit
breaker as shown. Fasten them using three panel mounting
screws (O), and connect the interlocking lever assembly to
the mounting panel using a tension spring.
Step 10: Rotate the key kits clockwise to allow some air for
cable installation. Place the cable on the interlock lever (N),
fix it using the fixing card (M), and then tighten it using the
interlocking screw (P).
Figure 8. Step 8
Figure 9. Step 9