Installing Battery Cabinets
3-3
EATON
Powerware
®
9390 Integrated Battery Cabinet (Models IBC-S and IBC-L) Installation Manual
S
164201536 Rev D
www.eaton.com/powerquality
5.
Turn each jacking bolt consecutively, two full turns, until the 4
6 supports clear
the floor by approximately 3 mm (1/8
I
).
W
A
R
N
I
N
G
RISK OF INSTABILITY. Turning the jacking bolts unevenly may cause the cabinet to become
unbalanced. To prevent tipping the cabinet, raise and lower the jacking bolts evenly.
C
A
U
T
I
O
N
CABINET MAY TIP. The battery cabinet should only be raised approximately 3 mm (1/8
I
)
above the floor (just enough to allow removal of the
4
6 supports).
6.
After the 4
6 supports clear the floor, remove the hardware loosened in Step 4.
Pull the 4
6 supports out from under the battery cabinet. Please discard or
recycle them in a responsible manner.
C
A
U
T
I
O
N
CABINET MAY FALL. Do not loosen the hardware attaching the side or front supports to the
cabinet base, or the front and side supports to each other, at this time. The cabinet must be
lowered by the jacking bolts before the supports can be removed.
7.
Carefully and evenly
lower the cabinet by turning each jacking bolt consecutively
two full turns (maximum)
until the casters contact the floor, and the cabinet is no
longer supported by the jacking bolts.
8.
After the battery cabinet is resting on the floor, remove the jacking bolts and
discard or recycle them in a responsible manner.
9.
Remove the hardware holding the front, rear and side supports to the cabinet
base. Discard or recycle the hardware and support brackets in a responsible
manner.
10.
The battery cabinet is now ready to be rolled to its final location.
11.
Repeat Steps 2 through 10 for each cabinet you are preparing to install.