I.B. ATS-V003

Page 6

Effective 6/98

SECTION 2: RECEIVING, HANDLING AND
STORAGE

2.1  RECEIVING

Every effort is made to insure that transfer switch equip-
ment arrives at its destination undamaged and ready for
installation. Crating and packing is designed to protect
internal components as well as the enclosure. Transfer
switch enclosures are skid mounted and suited for fork
lift movement. Care should be exercised, however, to
protect the equipment from impact at all times. Do not
remove protective packaging until the equipment is
ready for installation.

When transfer switch equipment reaches its destination,
the customer should inspect the shipping container for
any obvious signs of rough handling and/or external
damage incurred during the transportation phase.
Record any external and internal damage observed for
reporting to the transportation carrier and Cutler-
Hammer, once a thorough inspection is completed. All
claims should be as specific as possible and include
shop order and general order numbers.

MAKE NOTE OF THE WARNING LABEL ATTACHED
TO THE TOP OF THE SHIPPING CONTAINER THAT
WARNS AGAINST DOUBLE STACKING TRANSFER
SWITCH EQUIPMENT.

A shipping label is affixed to the top of the shipping con-
tainer which includes a variety of equipment and cus-
tomer information, such as General Order Number
(GO#) and Catalog Number (Cat#). Make certain that
this information matches other shipping paper informa-
tion.

Each transfer switch enclosure is bolted through its top
and bottom mounting flanges to a rigid wooden pallet.
The pallet is open at two ends for movement by a fork
lift. Heavy duty cardboard sides surround the enclosure
and are further supported with reinforced cardboard cor-

ner posts. An egg crate design cardboard protector cov-
ers the entire top of the enclosure with additional card-
board protectors over the indicating light panel and
operating handle. A heavy duty cardboard lid covers the
entire opening. The shipment is secured and further pro-
tected with shrink wrap. Do not discard the packing
material until the equipment is ready for installation.

Once the top packaging is removed from the shipment,
the enclosure door can be opened. A plastic bag of doc-
uments will be found within the enclosure, usually
attached to the inside of the door. Important documents,
such as test reports, wiring diagrams, appropriate
instruction leaflets and a warranty registration card, are
enclosed within the bag and should be filed in a safe
place.

2.2  HANDLING

As previously mentioned, transfer switch equipment is
packaged for fork lift movement. Protect the equipment
from impact at all times and do not double stack. Once
the equipment is in the installation location and ready to
be installed, packaging material can be removed. Once
the enclosure is unbolted from the wooden pallet, it can
be hand moved to its installation position. Be careful not
to damage the top or bottom enclosure mounting
flanges. Refer to Section 4 of this manual for specific
installation instructions.

2.3  STORAGE

Although well packaged, this equipment is not suitable
for storage outdoors. The equipment warranty will not
be applicable if there is evidence of outdoor storage. If
the equipment is to be stored indoors for any period of
time, it should be stored with its protective packaging
material in place. Protect the equipment at all times from
excessive moisture, construction dirt, corrosive condi-
tions and other contaminants. It is strongly suggested
that the package protected equipment be stored in a cli-
mate controlled environment of -20° to 85° with a rela-
tive humidity of 80% or less. Do not, under any circum-
stances, stack other equipment on top of a transfer
switch equipment enclosure, whether packaged or not.

!

CAUTION

Содержание Cutler-Hammer ATVSKDA30300XSU

Страница 1: ...I B ATS V003 Effective June 1998 Supersedes ATS VOO1 dated July 1997 Cutler Hammer Instructions for Cutler Hammer Transfer Switch Equipment 30 1000 Amperes...

Страница 2: ......

Страница 3: ...HAT CAN CAUSE DEATH OR SEVERE PERSONAL INJURY FOLLOW PROPER INSTALLATION OPERATION AND MAINTENANCE PROCEDURES TO AVOID THESE VOLTAGES WARNING TRANSFER SWITCH EQUIPMENT COVERED BY THIS INSTRUCTION BOOK...

Страница 4: ...ontacts 8 3 2 3 Vertical Design Transfer Mechanism 8 3 2 4 Horizontal Design Transfer Mechanism 8 3 3 Voltage Selection Panel 9 3 4 Logic Panel 9 3 5 Options Non Logic Panel 9 3 6 Enclosure 11 3 7 Sta...

Страница 5: ...03 Page v Effective 6 98 Page SECTION 6 TESTING AND PROBLEM SOLVING 6 1 Testing 26 6 2 Problem Solving 26 6 2 1 Transfer Switch Appears Inoperative 26 SECTION 7 MAINTENANCE 7 1 Introduction 28 7 2 Pro...

Страница 6: ...oor Closed 11 4 1 Enclosed Automatic Transfer Switch Dimensions and Approximate Weights 14 4 2 Vertical Design Power Panel Mounting Reference in Inches mm 15 4 3 Vertical Design Load Lug Assembly Show...

Страница 7: ...FAMILIARIZE PERSON NEL WITH THE STYLE OF PRESENTATION THIS WILL HELP TO INSURE THAT PERSONNEL ARE ALERT TO WARNINGS WHICH APPEAR THROUGH OUT THE DOCUMENT IN ADDITION CAUTIONS ARE ALL UPPER CASE AND B...

Страница 8: ...ly Operated just described except that an electrical operation feature is added The switch electrically transfers power when an appropriate pushbutton on the front of the enclosure is pushed If necess...

Страница 9: ...3 0225 B S U The catalog number ATVSKDA30225BSU describes an Automatic Transfer Switch with the switching devices mounted vertically in the enclosure The intelligence represented by the control panel...

Страница 10: ...g Fixed Mount Molded Case A Two 2 30A 0030 120VAC 60Hz A No Enclosure K UL Listed U Switches Both Power Sources 70A 0070 208VAC 60Hz B Type 1 S Three 3 100A 0100 600VAC 60Hz E Type 12 J UL Recognized...

Страница 11: ...I B ATS V003 Page 5 Effective 6 98 Figure 1 4 Horizontal Design Automatic Transfer Switch Equipment 30 150 Amperes...

Страница 12: ...ire top of the enclosure with additional card board protectors over the indicating light panel and operating handle A heavy duty cardboard lid covers the entire opening The shipment is secured and fur...

Страница 13: ...pecific type that will be discussed in this section The enclosed automatic transfer switch consists of three basic panels interconnected through connector plugs and mounted in an enclosure Figures 1 3...

Страница 14: ...g device are joined with a bus bar assembly to form a common load termi nal location either top or bottom Figure 4 3 Horizontally mounted switching devices are also mechanically and electrically inter...

Страница 15: ...sented in separate documents IQ Transfer Instruction Book Solid State Instruction Leaflet Micro processor Based Instruction Leaflet 3 5 OPTIONS NON LOGIC PANEL Switch options which are not part of the...

Страница 16: ...cy side only N Normal side only 18 IQ Metering I IQ Generator Normal Only J IQ Generator Emergency Only K IQ Generator Both N E Selectable O IQ Analyzer Normal Only P IQ Analyzer Emergency Only Q IQ A...

Страница 17: ...els per both the Uniform Building Code and the California Building Code 3 6 ENCLOSURE The rugged steel switch enclosure is supplied with three door hinges regardless of enclosure size to insure proper...

Страница 18: ...110 for emergency and stand by power systems and NFPA99 for health care facilities when ordered with the appropriate options Since Cutler Hammer Automatic Transfer Switches uti lize specially designed...

Страница 19: ...any doubts as to location suitability discuss it with your Cutler Hammer representative Check to make certain that there are no pipes wires or other mounting hazards in the immediate mounting area tha...

Страница 20: ...9 17 5 445 61 1549 26 660 19 63 499 8 203 4 00 102 11 279 16 00 406 59 86 1520 430 195 MA 600A 36 25 921 16 88 429 17 5 445 73 1854 26 660 20 63 524 8 203 4 75 121 12 305 16 00 406 71 86 1825 525 238...

Страница 21: ...bolts Step 4 While still supporting the enclosure install the two lower mounting bolts in the lower mounting flange but do not completely tighten Use shims if required to prevent deformation of the en...

Страница 22: ...e enclo sure and the power panel mounting provisions available for both top and bottom entry It will facili tate re installation of the power panel Step 4 Remove the operating mechanism from the front...

Страница 23: ...1 Power Panel Torque Switching Device in lb Nm Type FD 10 13 Type KD 20 27 Type LD 25 33 8 Type MA 25 33 8 Type ND NB 25 33 8 Table 4 1 Bolted Bus Connection Torque Requirements Figure 4 4 Typical 225...

Страница 24: ...ack of the enclosure replace and tighten the four mounting bolts removed previously in Step 3 Step 11 Attach the neutral strap to the back of the enclosure through the upper bonding hole which may or...

Страница 25: ...cting to the unit to insure that conductors or cable insulation have not been damaged while being pulled into position Step 5 Carefully strip insulation from the power cables Avoid nicking or ringing...

Страница 26: ...IN FIGURE 4 1 RUNNING THE CABLES IN PLACES NOT RECOMMENDED COULD INTERFERE WITH THE PROPER OPERATION OF THE TRANSFER SWITCH CHECK THE TRANSFER SWITCH EQUIPMENT NAMEPLATE FOR RATED VOLTAGE IT SHOULD BE...

Страница 27: ...p Voltage Selection Panel to the right of the power panel Seven front accessible taps from 208 to 600 volts AC are provided Figure 3 4 A small discon nect plug is provided to change from one voltage t...

Страница 28: ...sm with a manual operating handle Figure 4 4 The manual operating handle can be used to create the rotational motion required to open and close the main contacts through a rigid mechanical interlockin...

Страница 29: ...tor equipped transfer switches are mounted external to the molded case switches and operated by the rotating lever Each limit switch is synchronized with its associat ed switch to operate when the swi...

Страница 30: ...s and utilizes the same designs as the switches described in Paragraphs 5 4 and 5 5 except that intelligence and supervisory capabilities are added to the switch by the addition of a logic panel in th...

Страница 31: ...tored to its operating range At preset levels the logic starts the return to the nor mal power source and normal transfer switch opera tion During this sequence the Emergency Power Source Switching De...

Страница 32: ...ANY VOLTAGE SOURCE WHILE PROBLEM SOLV ING ONLY PROPERLY TRAINED PERSONNEL FAMILIAR WITH THE TRANSFER SWITCH EQUIPMENT AND ITS ASSOCIATED EQUIPMENT SHOULD BE PERMIT TED TO PERFORM THE PROBLEM SOLVING F...

Страница 33: ...ts Determine the cause and rectify if possible Replace defective components after the cause is determined Step 5 Manually ratchet the mechanism to the NOR MAL position Verify whether or not the system...

Страница 34: ...ion by this type of equipment inspection and maintenance checks should be made on a regularly scheduled basis Since equipment maintenance will consist mainly of keeping the equipment clean the frequen...

Страница 35: ...Inspect molded case switching devices for dust Remove dust dirt soot grease moisture and corrosion dirt soot grease moisture or corrosion contamination from the surface of the switching device using...

Страница 36: ...I B ATS V003 Page 30 Effective 6 98...

Страница 37: ...I B ATS V003 Page 31 Effective 6 98...

Страница 38: ...I B ATS V003 Page 32 Effective 6 98...

Страница 39: ......

Страница 40: ...e contract between the purchaser and Cutler Hammer NO WARRANTIES EXPRESSED OR IMPLIED INCLUDING WARRANTIES OF FITNESS FOR A PAR TICULAR PURPOSE OR MERCHANTABILITY OR WARRANTIES ARISING FROM COURSE OF...

Отзывы: