Eaton 93PM Universal Integrated Battery Cabinet (IBC-LW and IBC-LHW) Installation Manual P-164000541—Rev 04
NOTE
In multiple IBC installations, route the battery interface wiring between IBCs through the
top of the adjacent IBC using the top inter-cabinet access pass-through (see
).
4.
Line-Up-and-Match Wiring.
Route the thermal sensor interface wiring from the UPS thermal sensor
(building alarm) interface terminals through the top inter-cabinet access pass-through (see
) of the
UPS cabinet and IBC to the IBC battery interface terminal block TB2. See
for terminal locations.
5.
Proceed to
.
6.
Top Entry Wiring.
Remove the top conduit plate (see
) from the top of the IBC. Identify all
conduit requirements and mark their location. Drill and punch all conduit holes in the top conduit plate prior
to mounting on the IBC. Install the conduit plate and install all conduit runs into the plate. Pull the wiring
through the conduit into the wiring area.
NOTE
In multiple IBC installations, route the battery interface wiring between IBCs through the
top of the adjacent IBC using the top inter-cabinet access pass-through (see
).
7.
Route the thermal sensor interface wiring from the UPS thermal sensor (building alarm) interface terminals
through the top of the IBC and the top IBC inter-cabinet wiring access pass-through (see
) to the
IBC battery interface terminal block TB2. See
for terminal locations.
8.
Proceed to
.
9.
Bottom Entry Wiring.
Remove the bottom conduit plate (see
) from the inside bottom of the
IBC. Identify all conduit requirements and mark their location. Drill and punch all conduit holes in the
bottom conduit plate prior to mounting on the IBC. Install the conduit plate and install all conduit runs into
the plate. Pull the wiring through the conduit into the wiring areas.
NOTE 1
In multiple IBC installations, route the battery interface wiring between IBCs through the
top of the adjacent IBC using the top inter-cabinet access pass-through (see
).
NOTE 2
In the following step, leave slack in the interface cables to allow breaker tray movement.
10. Route the thermal sensor interface wiring from the UPS thermal sensor (building alarm) interface terminals
through the bottom of the IBC to the IBC battery interface terminal block TB2. See
for terminal
locations.
11. Connect the thermal sensor interface wiring to the IBC thermal sensor interface terminals. See
for termination requirements.
For a detailed view of the IBC terminal block, see
12. Connect the thermal sensor interface wiring to the UPS thermal sensor interface (building alarm) terminals.
Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in paragraph
, for UPS cabinet termination requirements
13. Reinstall the internal safety shield panel removed in
of paragraph
Line-Up-and-Match Power Wiring
14. Install the front door (previously removed) by carefully lowering the door onto the bottom screws. Secure
the top of the door with the four retained screws and tighten the bottom screws.(see
).
15. Once the battery cabinets are installed and wired, return to the applicable Eaton 93PM UPS Installation and
Operation manual, listed in paragraph
, to complete the UPS wiring.