2.
Install suitable cable glands into the gland plate.
3.
Route the cables through the glands.
4.
Connect the cables to the respective terminal blocks, see Figures in
section
5.
Route the communication
cables to the front of the unit
through the cable clips at the
back of the unit and through the
oval hole at the top.
6.
Connect the communication cables to the respective terminals and
peripherals. For detailed information, see Figures
and
Sections
.
7.
Assemble the internal batteries
into the battery trays. Connect
the battery blocks in series
within the battery tray. Only use
cables specified by Eaton. Note
that the battery trays may differ
from the illustration.
8.
Slide the internal battery trays
into place and mount the locking
brackets.
Eaton 91PS/93PS UPS 8–40 kW
User's and installation guide
©
Eaton Corporation plc 2018. All rights reserved.
Revision: 005
Document ID: P-164000493
57 (117)