Before Energizing

Energizing

7-

 It is recommended that no energy is applied 

to the line even if the insulation resistance test 

described in page 12 section 2 successfully 

completed.

8-

 When the equipment is energized for the 

first time, qualified electrical personnel must be 

present. If short circuits and earth faults due to 

damage or poor installation practices are not 

detected in the exit procedure, serious damage 

may occur when the power is turned on.

9-

 When the power is supplied, the busway 

must not have an electrical load. Since the 

busway typically runs through several rooms 

and ground level, care must be taken to see 

that all devices supplied by the busway path 

are in the "OFF" position.

10-

 The equipment must be energized in 

sequence starting from the welding end of the 

system and working towards the load side. In 

other words, it energizes the main devices, then 

the feeder devices and then the branch-circuit 

devices. Turn the devices to the "ON" position 

with a solid positive motion.

11-

 Once all overcurrent devices have been 

switched on, loads such as lighting circuits, 

contactors, heaters and motors can be turned 

ON.

12-

 When properly used, the busway will have 

a moderate hum. Excessive noise may be 

an indication of hardware that has not been 

extruded or incorrectly mounted metal parts.

13-

 All busway ratings, routings and supporting 

systems  should  be  checked  as  per  final 

isometric drawings.

14-

 All busway ratings, routings and supporting 

systems  should  be  checked  as  per  final 

isometric drawings.

15-

 All busway system should be checked 

visually to be certain that they are clean 

and secure. Loose and/or contaminated 

connections increase electrical resistance 

which can cause overheating.

 

16-

 Any type of blower or compressed air 

should not be used to avoid blowing dust into 

busway joints, tap off boxes or circuit breakers. 

If there is accumulation of dust and dirt, clean 

it off by using a soft brush, vacuum cleaner, or 

clean lint free rags. 

17-

 All joints should be correctly tightened 

according to the torque value given and should 

be marked. Then install the locking plates 

correctly.

18-

 All Tap Off boxes fed from the busway 

should be on ''OFF'' position.

19-

 The busway runs should be isolated by 

disconnecting all connections to transformers, 

switchboards, meters, etc.

20-

 Insulation resistance test with an insulation 

resistance test equipment rated 1000V AC 

should be conducted to verify the integrity 

of the system.This test should be performed 

between phases, neutral and earth. Permanent 

records should be kept of resistance readings. 

If the insulation reading appears to be lower 

than 1 megaohm, then the cause should be 

investigated.

21-

 The system phase squence should be 

checked in order to match the busway phases 

sequence before reconnecting all connections 

to transformers, switchboards, meters, etc.

Содержание E-LINEKX-III

Страница 1: ...www eaeusa us E LINEKX III MANUAL...

Страница 2: ...E LINEKX III...

Страница 3: ...Of Special Lengths Offset Sizing Mounting Instructions For Joints Bolt on Plug in Points To Be Taken Into Consideration After Installation Standard Application Precautions Plug in Busplug Busplug Cabl...

Страница 4: ...nts in Istanbul The components that you have purchased are manufactured by a completely environment conscious with the relevant Environmental management Standards and accordance with the principles of...

Страница 5: ...which will result in personal injury if the instructions are not followed This is the safety alert symbol It is used to alert you to personal injury hazards Obey all safety messages that follow this...

Страница 6: ...ed only by qualified electrical personnel Handle this equipment carefully and install operate and maintain it correctly in order for it to function properly Neglecting fundamental installation and mai...

Страница 7: ...rized to test energize clean ground label and lock the system and equipment suitable for occupational safety applications Be trained in the use and maintenance of personal protective equipment such as...

Страница 8: ...rement Rain Drops Please use canopy for outdoor applications Please use porch for outdoor Please use porch for outdoor Please use canopy for building expension points Chemicals Urine Water CLOSE INDIR...

Страница 9: ...ng List or any piece is damaged during transportation Insurance Company must be informed immediately for proper reporting with all required documents for further action 4 All busway straight lengths a...

Страница 10: ...he load is stable and safely secured Then adequate sling and slinging method can be used for shifting from one place to another 6 The removal of the products from one floor to the other floor must be...

Страница 11: ...for weight specifications If using a forklift position the plug in unit on the forks to distribute the weight properlyTake care not to damage the metal housing Avoid using objects with sharp edges to...

Страница 12: ...ansition of building dilatations appropriate dilatation module should be chosen Please contact our company for support 6 Busway system should be handled with care either by forklift crane or any other...

Страница 13: ...e installation Micrometer type adjustable calibrated torque spanner 9 a inch square drive size 10mm 13mm and 9 b 19mm socket 9 c Drilling Machine 9 d Size 10mm Spanner Socket 9 e Screwdriver 9 f Hoist...

Страница 14: ...Washer 7 Alignment Pin removable 8 Conductors 9 IP55 Nut Locking Piece 10 Protection Plastics 11 IP55 Joint Cover Gasket 12 Alignment Pin Slot NB Protective covers 10 are discarded KX busway are manu...

Страница 15: ...KX IIIMANUAL www eaeusa us 13 Installation General Overview Of The Joint Bolt on Box Fixing Point Plug in Box Fixing Point Use special hand clamps if it is difficult to move...

Страница 16: ...ses please contact our company for technical support and technical information Note Please send a drawing for combined offsets when ordering Indicate bolted and non bolted ends on the drawing 325 A X...

Страница 17: ...ock joints 3 Remove the nut locking piece on the busway joint and loosen the joint Remove the protective covers after loosening the joint 4 Ensure that the insulation plates of the joint are not crack...

Страница 18: ...e bolt per phase the bolts should be tightened by hand to approximately 20 30 Nm as per the sequence shown above Then finally torque to 83Nm using the same sequence 12 Remove the joint covers and reve...

Страница 19: ...Joints have been done according to manual and applied related Nm value to the main bolts Tarih Date Ad Soyad First Last mza Signature Ek montaj talimat na uygun yap lm t r ve yanda yaz l Nm de erinde...

Страница 20: ...e insulation test is completed successfully 2 3 After the busway system is energized loads must be switched in sequence main and sub feed 2 4 When the busway is used properly it will have a moderate h...

Страница 21: ...ns than original tap off boxes to supply energy from the busway 6 Current rating of the busway run should be equal to the rating of the breaker Do not exceed busway nominal current during operation 7...

Страница 22: ...DARD IP55 IP65 Vertical Shaft Application Pressure Water 3 Min 1 The neutral bar of KX busway shall be at the bottom for horizontal busway lines and on the left for vertical busway lines Figure 1 2 In...

Страница 23: ...confirm that the power is off Do not install plug in unit without circuit breaker installed Do not install plug in unit with cover open or removed Failure to follow these instructions will result in...

Страница 24: ...Frequency Protection Degree Wire 1000 V 50 60 Hz IP55 Ui f IP 3P N PE Housing E L E K T R K 1 EAE tap off boxes are not equipped with any protective device unless they are required by customer Any typ...

Страница 25: ...e fixing screw of plug in tap off point cover using cross recessed screw driver 3 Throw the contact protection cover to the recycling waste bin 4 Place the KXP Plug in tap off box to the holes on the...

Страница 26: ...way 6 Push the box to the busway housing click sound will be heard from the locking parts on the box ensure the interlock betwe en the box and the housing then tighten the screw 6 a 6 a 6 b 6 b CLICK...

Страница 27: ...IDENTAL RESPONSE TO BE CONTACTED BY PARTS UNDER ELECTRICALLY FOLLOW ALL MANUFACTURER S WARNINGS AND INSTRUCTIONS 4 Resistance testing is to be carried out with a resistance tester of 1000 volts per pa...

Страница 28: ...l parts 13 All busway ratings routings and supporting systems should be checked as per final isometric drawings 14 All busway ratings routings and supporting systems should be checked as per final iso...

Страница 29: ...such as lighting circuits contactors heaters and motors may be turned ON 6 EAE busway system is particularly quiet when operating normally In some installations however there may be a moderate hum Exc...

Страница 30: ...erly rated voltage sensing device at all line and load side fuse clips to confirm that the plug in unit is off Never operate the plug in unit with the door open Failure to follow these instructions wi...

Страница 31: ...A 70E NOM 029 STPS 2011 or CSA Z462 Turn off the plug in unit Always use a properly rated voltage sensing device at all line and load side fuse clips to confirm that the plug in unit is off Never oper...

Страница 32: ...pairs it may be desirable to perform an infrared temperature test on all electrical connections Do this after the busway has been re energized and has reached a stable operating temperature 7 Refer to...

Страница 33: ...cleaner or clean lint free rag Do not use a blower or compressed air 1 An external inspection of the system should be carried out once a year 2 Any dripping or other source of moisture onto the buswa...

Страница 34: ...tors 5 full size conductors PE 100 earth conductor housing 3 3 Insulation Insulation system is suitable for 600 V continuous operation Specially formulated Class B epoxy insulation has been applied as...

Страница 35: ......

Страница 36: ...ons or changes on this catalogue without any prior notice EAE Elektrik A S Akcaburgaz Mahallesi 3114 Sokak No 10 34522 Esenyurt Istanbul TURKEY Tel 90 212 866 20 00 Fax 90 212 886 24 20 EAE USA Inc 56...

Отзывы: