2. Installing the IP DSLAM
Hardware Installation
This chapter describes how to install the 24 ports VDSL IP DSLAM to establish network connection. You may install
the IP DSLAM on any level surface (table, shelf, 19 inch rack or wall mounting). However, please take note of the
following minimum site requirements before you begin.
Pre-installation Requirements
Before you start actual hardware installation, make sure you can provide the right operating environment, including
power requirements, sufficient physical space, and proximity to other network devices that are to be connected. Verify
the following installation requirement:
Verify the following installation requirements:
•
Power requirements: AC 100V to 240 V at 50 to 60 Hz.
The Switch power supply automatically adjusts to the input voltage level.
•
The IP DSLAM should be located in a cool dry place, with at least 10cm/4in of space at the front and
back for ventilation.
•
Place the IP DSLAM out of direct sunlight, and away from heat sources or areas with a high amount of
electromagnetic interference.
•
Check if network cables and connectors needed for installation are available