BEFORE YOU START:

 

 

• 

Read all instructions carefully

 

• 

Identify all parts and check quantities against parts list

 

• 

Select a level site

 

• 

Do not mark cladding with pencil as lead can cause corrosion to cladding

 

• 

During assembly, ensure all drill filings are removed between  layers of steel, before riveting together

 

 

 

SAFETY:

 

 

• 

Do not attempt to build your shed in high winds

 

• 

Beware of sharp edges, we recommend that you use gloves

 

• 

Protect your eyes and ears

 

• 

For ease of assembly, use a friend to help 

 

 

 

TOOLS REQUIRED:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

WARRANTY REQUIREMENTS

:

 

 

The following maintenance process needs to be adhered to, to qualify for the steel warranty of your Duratuf Guardian 

shed.

 

 

 

• 

Wash all surfaces annually using a hose and soft nylon brush.

 

• 

Within 2 km of coast –

 

wash every 3 months as above. After a storm, wash the cladding and the gutters as soon 

as possible to remove any highly corrosive salt deposits.

 

• 

Volcanic Ash Fallout –

 

wash as soon as possible, removing fall out from roof and gutters.

 

• 

Do not allow manures, chemicals or other corrosive materials to have direct contact with cladding

.

 

CONGRATULATIONS ON PURCHASING A DURATUF GUARDIAN SHED. 

 

BEFORE YOU BEGIN THE ASSEMBLY PLEASE NOTE SOME IMPORTANT POINTS:

 

2

 

DRILL

 

RIVETER

 

3.5mm DRILL BIT

 

HAMMER

 

LADDER

 

TAPE MEASURE

 

HEX DRIVE

 

NAIL PUNCH

 

SQUARE DRILL BIT

 

SKILL SAW 

 

(timber floor only)

 

Содержание Gurdian Sheds GG101

Страница 1: ...ASSEMBLY INSTRUCTIONS GG101 BASE SIZE 3 190m x 3 020m...

Страница 2: ......

Страница 3: ...process needs to be adhered to to qualify for the steel warranty of your Duratuf Guardian shed Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as...

Страница 4: ...1 920m 4 Side Wall Angle 1 980m 4 Side Wall Angle 2 040m 4 Roof 1 600m 12 Roof 1 Pan 1 600m 2 Door Sheet Narrow 1 850m 3 Door Sides 1 850m 4 Door Jamb 1 890m 2 Door Brace 1 160m 2 Door Brace 0 915 2...

Страница 5: ...CRIPTION QTY DIAGRAM CHECKED Front Back Bottom Plates H4 Green 3 190 m 2 Front Back Top Plate H1 Red 3 190 m 2 Side Wall Bottom Plates H4 Green 3 020 m 2 Side Wall Top Plates H1 Red 3 020 m 2 Ridge Be...

Страница 6: ...Top Plate Side Top Plate Front Bottom Plate Front Bottom Plate Side Back Wall Sheets 6 Sheets 1 x 1Pan Sheet Front Wall Sheets 1 Sheet 1 x 1Pan Sheet Door Jambs Front Wall Sheet x 2 Door Side Flashing...

Страница 7: ...hrough from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bottom plat...

Страница 8: ...g 1 STEP 4 On the back of the door place door braces in posi tion as shown in fig 4 Ensure that the top and bottom ends of the braces are under the door flashings as shown in fig 5 and opposite ends o...

Страница 9: ...e wall sheet overhang the Top Plate by approx 15mm as shown Check that the Top Plate is straight then nail the Wall sheet to the Top Plate 2 clouts per pan see fig 1 Standard Shed Bottom Plate will pr...

Страница 10: ...wall sheets to the Top Plate using two clouts per pan STEP 4 Nail the wall sheets to the Bottom Plate at each end ensuring that each side of the wall sheets overhangs the Bottom Plate by 15mm and tha...

Страница 11: ...by 15mm as shown Nail wall sheets to Top Plate two clouts per pan Nail the wall sheets to the Bottom Plate making sure that the Plates are the correct distance apart and that the sides of the wall sh...

Страница 12: ...2 per join screw the Top and Bottom Plates together in the corners STEP 2 Repeat Step 1 with the second Side Panel ensuring that the Side Panel overlaps the Back Wall Panel STEP 3 Stand up the Front...

Страница 13: ...90 m Ridge Beam 2 x 0 200 m Jack Studs 8 x 75mm Screws 36 x 50mm Roofing Screws 74 x Rivets 44 x 50mm Clouts 12 JACK STUD TOP PLATE RIDGE BEAM fig 1 fig 2 STEP 2 Position the first Roof Sheet so that...

Страница 14: ...l holes using a 3 5mm drill bit Use Roofing Screws on all other ribs and pans Ensuring screws are not overtightened as this can damage the seal and cause the shed to leak fig 1 SIDE WALL FRONT WALL BA...

Страница 15: ...h end with two 75mm nails Check that the shed is sitting level and square Check that the diagonal Bottom Plate measurements are the same This ensures that the shed base is square Place the Floor Board...

Страница 16: ...less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Faste...