Step 3:

 

Select two 1.715m Base Plates (Green) and two 
1.715m Top Plates (Red). With front wall lying on 
the  ground,  nail  Plates  to  frame.  Ensure  Green 
joins to Green and Red joins to Red.

 

Step 4:

 

Position  the  back  wall  frame  on  top  of  plates. 
While someone supports frame, nail in place. 

 

Step 5:

 

Carefully roll frame over onto its base. (Pieces of 
timber  from  the  packaging may  be  used  to  tem-
porarily  brace  the  frame  before  rolling  it  over). 
Position 1.625 End Wall Nogs .883m down from 
Top Plate and nail in place. If fitting a Kiwi Floor, 
fit Floor Joists now. Space joists equally and nail 
in place using three 75mm nails per end.

 

fig. 1

 

2

 

Step 6:

 

Position  a  Jack  Stud  on  each  end  of  Ridge 
Beam  and  nail  in  place  using  two  75mm  nails 
each end (

fig.  1

). Turnover Ridge Beam / Jack 

Studs, position centrally on 1.715m Top Plates 
and  nail  to  Top  Plates  using  two  75mm  nails 
per Jack Stud. 

 

Note:

 

If fitting a window in the Back Wall, there will be no centre stud on that side. Instead nail in a full length Nog 
(3.290) using Window Studs (.883) to get correct height. Position one Window Stud centrally beneath the Nog 
and nail in place. Further window studs and Nogs are fitted after the cladding is on.

 

Note:

 

For  sheds  with  the  Raised  Floor  Modification  option  the  studs  will  be  1.780m  long  to  allow  the  Wall  Sheets  to 

 

protrude 20mm below the Bottom Plate. Refer to Raised Floor Modification section (Page 15). 

 

Step  1:  Back  Wall:

  Select  one  3.380  Base  Plate 

(Green), one  3.380m Top Plate (Red)  and three 
Studs (Yellow). Lay out Plates and two Studs on 
a flat surface and nail together  using two  75mm 
nails per join. Nail in remaining centre stud using 
1.622m  Nogs  to  get  correct  position.  Position 
Nogs .883m from Top Plate and nail in place. 

 

Step  2:  Front  Wall:

  Select  one  3.380  Base  Plate 

(Green), one 3.380m Top Plate (Red), four Studs 
(Yellow),  one  .785m  Nog  and  one  1.622m  Nog. 
Nail studs to each end of Plates. Nail in remain-
ing two studs using Nogs to get correct position. 
Position  Nogs  .883m  down  from  Top  Plate  and 
nail in place. 

 

Содержание SHEDS MK3

Страница 1: ...Quality Built In ASSEMBLY INSTRUCTIONS MK3 BASE SIZE 3380mm x 1715mm ...

Страница 2: ... checklist If you are making your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools with care Use a Safety Trip Switch It is easier and quicker if this shed is erected by two people Your shed must be level Achieve this by either levelling the ground or by using blocks If you shed is t...

Страница 3: ... 0 588 x 0 150m 0 710 x 0 240m 1 Fixed Window Frame Glaze Beads Glass Louvre Window Frame Glass Over Panel Window Hardware Pack 2 000m 1 000m 1 000m 1 175m 1 Roof Sheets Flat Roof Sheet Clear Roof Panel Ridge Flashing Clear Roof Hardware Pack Security Single Door Hardware Pack Alarm MA20 Shed light Bolt Down Kit Peg Down Kit 188 50mm Flooring Nails 12 75mm Flooring Nails KIWI MK3 PARTS LIST 1 Dura...

Страница 4: ... 1870 for Raised Base Plate only 45 45 1622 3380 45 45 45 BACK WALL 883 45 1622 1900 or 1870 for Raised Base Plate only 1 810 YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW 45 45 785 3380 45 45 45 FRONT WALL 883 45 795 45 1622 ...

Страница 5: ...itting a window in the Back Wall there will be no centre stud on that side Instead nail in a full length Nog 3 290 using Window Studs 883 to get correct height Position one Window Stud centrally beneath the Nog and nail in place Further window studs and Nogs are fitted after the cladding is on Note For sheds with the Raised Floor Modification option the studs will be 1 780m long to allow the Wall ...

Страница 6: ...k on a wall sheet means to use minimum nails hammered partly in to hold Wall Sheets in position Should a Wall Sheet need to be re positioned the nails can easily be prized out If a window is required identify Wall Sheet s with window hole pre cut Lean up Wall Sheets where window s are to be located Note When fitting Gable End Sheets ensure they overlap correctly fig 1 The overlap direction may dif...

Страница 7: ... top of Top Plate tack in place Repeat with remaining sheets Step 3 End Walls Lean Gable Wall Sheets against the shed to form gable shape With the LIP flush with side of Stud tack in place ensuring the bottom of the Wall Sheet is 10mm above the bottom of the Bottom Plate Tack on re maining Wall Sheets Repeat with other gable end If fitting a window nail in Window Studs and Nog now Refer to Window ...

Страница 8: ...ill holes in each corner and nail Win dow Frame to framing using 50mm nails Step 4 If the Window is in the gable end temporarily position the Over Panel above Window Frame Following the same angle as the gable mark and cut to suit Step 5 Rivet Over Panel to the Window Frame with riv ets 588mm Step 1 Lay out the two window studs 883mm and Nog 634mm on a flat surface Position Nog and nail in place u...

Страница 9: ...ttom Plates and hard against Stud Attach Door Jamb Flashing with three rivets into Rib on the outside and three 30mm clouts into studs on the inside Repeat with the other Door Jamb Step 3 Fit Corner Flashing 101 over corner Ribs with the top flush with the top of the Top Plate Rivet in place with six rivets three each side Repeat with other three Corner Flashings When fitting Corner Flashings on f...

Страница 10: ...he Door Guide 108 over the Guide Brackets on the door and align the end of the Door Guide 20mm in from left side of the left hand door jamb flashing Step 6 Lift the door guide up approximately 3mm so that the Door will Slide freely Pre drill a hole through the door guide and the end rib of the cladding and screw in place using a 45mm screw Step7 Slide the door to the centre ensuring that it slides...

Страница 11: ... pieces of timber from the packaging Step 3 Starting from the left hand end centralize Roof on Ridge Beam Ensure Roof is tight against end Wall Sheets predrill then nail one 50mm Clout through Rib into the Ridge Beam At the back line up Ribs on the Roof Sheet with the Ribs on Wall Sheet Using one 50mm Clout nail through Rib into Back Top Plate Repeat at the front Note The 6 x 50mm Clouts on end ri...

Страница 12: ...rews Screw one 50mm roofing screw into ridge beam through each rib on overlap one screw per sheet Mould the soft edge on the flashing down into the pans of the roof sheet to prevent roof leaks Step 4 Continue to fasten roof sheets as per step 4 on previous page pg10 Note When screwing through the clear panel pre drill a 6mm hole TOP PLATE JACK STUD RIDGE BEAM 30mm CLOUT RIDGE FLASHING ROOFING SCRE...

Страница 13: ... straight then rivet to Roof one rivet every second Rib Note MK2 shown Note MK2 shown MK3 FLOOR Optional Step 1 Place shed in final position Check the diagonal measurements are the same and the shed is level before fitting Floor It is recommended that the shed is anchored down with either a Duratuf Bolt Down Kit or Duratuf Peg Down Kit depend ing on what the shed is sited on Step 2 Lay a Floor Boa...

Страница 14: ... into Joists Measure and cut Floor Flashing 110 to fit in between Door Jamb Flash ings and nail in place using 50mm Clouts MK3 HASP STAPLE Using six rivets and one 50mm clout attach hasp to Door Jamb Flashing and the staple to the Door as shown Note see below for security option SECURITY DOOR Optional Step 1 Attach T locking handle with two 8x10mm screws Slide hook onto square shaft and secure wit...

Страница 15: ...d on a purpose built floor concrete cob bles ply etc the Wall Sheets will protrude 20mm below the Base Plate This will stop water flowing in between the Base Plate and Floor The Floor should be made 15mm smaller than Base Size Note Although it is not essential fitting Damp Proof Course in between the Base Plate and the Floor will give add ed protection against moisture CLEAN UP Remove all swarf dr...

Страница 16: ...arried out in accordance with instructions below Should the cladding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or repairing the defective product The balance of the original warranty will cover any repaired or replaced material Riverlea Group Ltd will not be liable for any consequential loss or damage labour or transport charg...