Place the switchgear on plain and horizontal concrete foundations or intermediate
frames with sufficient capacity to avoid the deformation of the switchgear cubicles.
Preliminary measures:
-
Check the completeness of the necessary components and tools.
Einzelteile:
1.
3 coupling isolation parts
2.
1 tube fitting lubricant
3.
3 tension springs
4.
6 cylinder head screws M8x50 with big discs, spring rings and half bolts
5.
5 spacing bush
6.
4 hexagon head screws M12x55 with spring rings and bolts
7.
1 hexagon head screw M12x70 with disc, 2 spring rings and 2 bolts
8.
2 distance sheet steel
9.
2 hexagon head screws M8x30 with spring rings and bolts
1 drawing HB71553-001 (appendix to this manual)
Assembly tools: (does not belong to the scope of delivery)
2 parallel clamps
4 spuare assembly aids (i.e. 25er spuare tube)
Screw wrench