System description
User Information
Climbing formwork 150F
Schematic workflow of climbing phases
Start-up phases
Typical phases
The 1st casting section is poured
without a climbing scaffold.
The 2nd casting section (and all further sec-
tions) are poured using the climbing scaffold.
The suspended platforms are mounted, and
then the 3rd section is poured.
The climbing scaffold is raised
to the next casting section.
The next casting section is poured.
9775-220-01
9775-241-01
9775-222-01
9775-243-01
9775-242-01