background image

3

MN3082

RTL Series

A Circulating Oil Inlet Kit is required for each pillow block for the 

Cool Lube 2 installation. Install the Circulating Oil Inlet Kit as 

shown in the Sleevoil Instruction Manual (see Figure 5).

RTL Circulating Oil Inlet Kit

Part No.

RTL 2-15/16” thru 5-7/16” Circulating Oil Inlet Kit

132203

RTL 6” thru 12” Circulating Oil Inlet Kit

132205

The user shall provide connection adapters and tee fittings to 

connect the supply lines to the circulating oil inlets. A tee fitting 

is required at the inlet connection because these pillow blocks 

have 2 circulating oil inlets. The tee fitting ensures both oil inlets 

receive an equal amount of oil. Flexible connections from the 

tee fitting to the oil inlets are recommended (see Table 4 for inlet 

connection size).

Table 4–RTL Series

Bore Size 

Number of 

Circulating 

Oil Inlets 

and Outlets

Circulating 

Oil Inlet 

NPT Size 

(Female)

Circulating 

Oil Drain 

Hole NPT 

Size

Alternate Oil 

Gauge Hole 

NPT Size

2-15/16"

2

3/4 - 14

1 - 11-1/2

3/4 - 14

3-7/16"

2

3/4 - 14

1 - 11-1/2

3/4 - 14

3-15/16"

2

3/4 - 14

1 - 11-1/2

3/4 - 14

4-7/16"

2

3/4 - 14

2 - 11-1/2

3/4 - 14

4-15/16"

2

3/4 - 14

2 - 11-1/2

3/4 - 14

5-7/16"

2

3/4 - 14

2 - 11-1/2

3/4 - 14

6"

2

1 - 11-1/2

2 - 11-1/2

3/4 - 14

7"

2

1 - 11-1/2

2 - 11-1/2

3/4 - 14

8"

2

1 - 11-1/2

2 - 11-1/2

3/4 - 14

9"

2

1 - 11-1/2

2 - 11-1/2

3/4 - 14

10"

2

1 - 11-1/2

2-1/2 - 8

3/4 - 14

12"

2

1 - 11-1/2

2-1/2 - 8

3/4 - 14

RXT Series

A Circulating Oil Inlet Kit is NOT required for these pillow blocks. 

The circulating oil inlets are machined into the housing and are 

plugged with pipe plugs as shown in the Sleevoil Instruction 

Manual (see Figure 6).
The supply line should be connected to the two inlets on the 

downswing side of the pillow block for base loaded applications, 

or to the two inlets on the upswing side for cap loaded 

applications.

The user shall provide connection adapters and tee fittings to 

connect the supply lines to the Sleevoil circulating oil inlets. A 

tee fitting is required at the inlet connection because these pillow 

blocks have 2 circulating oil inlets. The tee fitting ensures both 

oil inlets receive an equal amount of oil (see Table 5 for inlet 

connection size).

Table 5–RXT Series

Bore Size 

Number of 

Circulating 

Oil Inlets

Circulating 

Oil Inlet 

NPT Size 

(Female)

Circulating 

Oil Drain 

Hole NPT 

Size

Alternate Oil 

Gauge Hole 

NPT Size

2-15/16"

2

1/2 - 14

1-1/4 - 11-1/2 1-1/4 - 11-1/2

3-7/16"

2

1/2 - 14

1-1/4 - 11-1/2 1-1/4 - 11-1/2

3-15/16"

2

1/2 - 14

2 - 11-1/2

2 - 11-1/2

4-7/16"

2

1/2 - 14

2 - 11-1/2

2 - 11-1/2

4-15/16"

2

1/2 - 14

2 - 11-1/2

2 - 11-1/2

5-7/16"

2

1/2 - 14

2 - 11-1/2

2 - 11-1/2

6"

2

3/4 - 14

2-1/2 - 8

2-1/2 - 8

7"

2

3/4 - 14

2-1/2 - 8

2-1/2 - 8

8"

2

3/4 - 14

2-1/2 - 8

2-1/2 - 8

9"

2

3/4 - 14

2-1/2 - 8

2-1/2 - 8

10"

2

1 - 11-1/2

2-1/2 - 8

2-1/2 - 8

12"

2

1 - 11-1/2

2-1/2 - 8

2-1/2 - 8

Figure 5 - RTL Circulating Oil Inlets

Figure 6 - RXT Circulating Oil Inlets

Содержание Cool Lube 2

Страница 1: ...dunderstandthismanualinitsentiretybeforeproceeding Failureto observethisprecautioncouldresultinseverebodilyinjuryorlossoflife RECEIVING INSPECTION 1 Carefully unpack the Cool Lube 2 system Inspect the...

Страница 2: ...ction Manual R Series Circulating Oil Inlet Kit Part No R Series 3 15 16 Circulating Oil Inlet Kit 432153 R Series 4 7 16 through 4 15 16 Circulating Oil Inlet Kit 430198 R Series 5 7 16 through 12 Ci...

Страница 3: ...10 2 1 11 1 2 2 1 2 8 3 4 14 12 2 1 11 1 2 2 1 2 8 3 4 14 RXT Series A Circulating Oil Inlet Kit is NOT required for these pillow blocks The circulating oil inlets are machined into the housing and a...

Страница 4: ...rt 434725 260W X 240V 1 PH Part 434726 Optional Temperature Oil Level Switch Part 434941 Connects to a control system not provided by Dodge in order to monitor oil level and temperature Replacement Fi...

Страница 5: ...AT EXCHANGER MOTOR 21 2 PRESSURE GAUGE 22 2 FLOW METER 1 2NPT 0 5 4 0 GPM 23 1 TOP PLATE 24 1 FILLER BREATHER 25 1 BALDOR PUMP MOTOR 26 1 CHECK VALVE 1 2 HP 7 PSI 3 8 HOSE 1 2 PIPE 1 2 NPT 1 2 NPT 5 G...

Страница 6: ...ery 4000 hours of operation More frequent cleaning is required if the system is used in a highly contaminated atmosphere such as a foundry or paper mill After the initial replacement the supply line f...

Страница 7: ...7 MN3082...

Страница 8: ...Dodge Industrial Inc 1061 Holland Road Simpsonville SC 29681 1 864 297 4800 All Rights Reserved Printed in USA MN3082 02 22 3082 0222 DODGE INDUSTRIAL INC AN RBC BEARINGS COMPANY...

Отзывы: