Dhatec V-Sup Скачать руководство пользователя страница 10

10 

 

Figure 10. Pipe on V-beam 

C.

 V-beam for pipe stringing 

Step C.1.    

Preparation of location 

 

Make sure the construction area is visibly marked and the transport and emergency routes are clearly indicated. 

 

Make sure the surface  on  which the  V-Sup  will  be installed  is 

levelled

, make sure that the maximum slopes 

named on page 5 are respected. 

Check the right-of-way (pipeline route) for any slopes.

 

 

Make sure the surface on which the V-Sup will be installed is 

flat

, unevenness in the terrain of maximum 20 mm 

are acceptable. Unevenness larger than 20 mm should be levelled out properly. 

 

Make sure the surface on which the V-Sup will be installed is 

free of ice, snow, oil, mud, algae

, or any other 

substances that have a negative influence on the friction. 

 

Make sure the surface on which the V-Sup will be installed is free of obstacles (such as wood, stones, gravel 
or any other obstacles). 

 

Make sure the minimum and maximum operating temperatures of respectively -30 and +45 

°

C are respected. 

 

Step C.2.    

Installation of the V-beams 

 

For pipe stringing, at least two V-beams per pipe are necessary.  

 

Make sure all  V-beams are 

free of ice, snow, oil, mud, algae, or 

any  other substances that have  a  negative 

influence on the friction. 

 

Make sure the V-beams segments are not damaged, deformed or worn down. 

 

The alignment of the V-beams is of vital importance for the safe functioning of the system. The V-beams needed 
for one pipe should be aligned parallel. 

 

 

To give the best support for the pipes, the V-beams have to be placed at a set distance according to the pipe 
length  and  the  amount  of  V-beams  needed.  The  distance  is  prescribed  as  a  percentage  of  the  pipe  length. 
Figure 7 shows the prescribed distances with 2, 3 and 4 supports.

 

 

 

 
 

 

 

 
 
 
 
 

 

 

Содержание V-Sup

Страница 1: ...jn Bayens 03 12 02 2018 Released Bas Coenen Martijn Bayens 04 02 04 2019 Released Bas Coenen Martijn Bayens Dhatec B V The following document shall be considered as copyright and the design right rese...

Страница 2: ...ur knowledge correct at the date of publication However Dhatec B V cannot be held responsible for consequences that follow from the claims that were made in this document Do not carry out any repairs...

Страница 3: ...support pipes during construction activities Supporting these pipes is not without risks If the pipes are not handled and supported carefully serious damages or injuries can occur The purpose of this...

Страница 4: ...e 90 C 194 F User actions Before installing a V Sup stack subject the parts to an extensive visual inspection and discard the parts that show product failures chapter A 2 The V Sup beams must be free...

Страница 5: ...be found in the following paragraphs of this chapter A General instructions for V Sup A 1 Equipment A 2 Product check B Installation of the V Sup B 1 Preparation of construction location B 2 Installat...

Страница 6: ...ing This means two beams will be placed directly on the ground after which a pipe can be placed on top of them The V Sup is capable of supporting pipes up to 2032 mm 80 A pipe has to be supported by a...

Страница 7: ...safe way check all products before using them Do that by looking at the next points The beams should always be able to lock into each other without any problems The beams should not show signs of exte...

Страница 8: ...cles such as wood stones gravel or any other obstacles To ensure a safety envelop large enough the use of the V sup is recommended within a temperature window of 30 C up to 45 C 22 F to 113 F Step B 2...

Страница 9: ...he V Sup stack are free of ice snow oil mud algae or any other substances that have a negative influence on the friction Make sure the V beam is free of ice snow oil mud algae or any other substances...

Страница 10: ...ure the surface on which the V Sup will be installed is free of obstacles such as wood stones gravel or any other obstacles Make sure the minimum and maximum operating temperatures of respectively 30...

Страница 11: ...ure the V Sup stacks are loaded carefully The V Sup can be loaded with all different lifting equipment hooks reach stacker vacuum lifter slings etc Make sure that during the lifting and loading proced...

Страница 12: ...12 Guidelines to check if V Sup is used properly Figure 15 Contamination in recesses Figure 13 Unevenness in terrain Figure 12 Correct V Sup stack Figure 14 Beams on their sides...

Страница 13: ...13 Figure 16 V Beam in outer recesses Figure 16 Correct V Sup Stack Figure 17 Beams placed next to recesses Figure 18 Stackable Beam left out of the stack...