Figure 12. Four-post threaded configuration
2
For each rail, attach the front and back flanges to the post flanges with two user-supplied screws at each end, item 2.
Z9100-ON system installation
You can mount the system in the 1U front-rack or 1U two-post flush and center configurations. The following is an example of a front-rack
configuration.
For the 1U two-post flush and center configurations, slide the system into the rails in the same manner as the four-post configurations.
1U front-rack installation
Configure the rails that are attached to the system.
1
Attach the inner chassis member switch rails to the Z9100-ON system.
Item 3 shows the detail for the front standoff with the locking tab.
Z9100–ON installation
23