ASSEMBLY AND OPERATING MANUAL DEGERtracker S60H CF
Page 16
5.93 m
5.93 m
5 Preparing for the assembly of the DEGERtracker
5.1
Notes on creating the base
The base may only be prepared by expert personnel.
Documentation can be downloaded from www.DEGER.biz
in the traders’ area.
Care must be taken to ensure sufficient space in the area around the DEGERtracker and module
area when mounting connection boxes or similar items.
5.1.1
Concrete base
A formwork and reinforcement diagram for the particular foundation, as shown below, can be obtained for
each DEGERtracker on request
– you must observe the instructions given in the diagrams! This diagram will
be sent with the order confirmation. The diagram shown is only intended as a sample drawing.
We recommend having the foundation reinforcement approved by a qualified engineer or technician before
concreting.
The necessary bearing capacity of the subsoil is 140 kN/m². The angle of internal friction is 30°. This values
must be checked for correctness and documented by the site manager in charge. A substratum expert has to
be contacted if there is any uncertainty.
In regions and with soils at risk of frost, further measures must be taken to ensure frost protection, e.g. frost-
proof sub-base or lean-mixed concrete fill down to the frost line.