Chapter 3 Installation
3.2.7 STEEL CABLE INSTALLATION
1 Open the cover of carriage and fix the carriage on the first tooth. Connect the steel cable and
tighten the nut.
2
Set the carriage on the lowest locking point, and then adjust the steel cables.
3 Ensure no cross and mistake installation of cables, also ensure the steel cables are on top the
pulley.
3.2.8 INSTALLATION OF OTHER PARTS
-Unlocking device installation:
1 Install safety part and steel cable according to unlocking device 1 and 2, and tighten the cable
with cable clip. (See picture 8 and picture 9)
Important notice:
Correct standard of unlocking adjustment is as follow: When nut of electromagnetic steel core is at
the end (see picture 9), two safety boards strike close to the carriage, to lock the carriage effective.
When the nut of electromagnetic steel core is at the root of thread, two safety boards can open
together and carriage lowers. The synchronization of two carriages depends on the force of steel
cables.
Install and fix four swing arms on carriage with hinge axis, and fix the support block.
Picture 6
(
oil pipe list and installation
)
Picture 7 oil pipe connection cable
Picture 9 (unlocking 2)
Picture 8
(
locking 1
)
Содержание LJCC2045A
Страница 1: ...1 TWO POST LIFT LJCC2045A U Us se er r s s m ma an nu ua al l Manufacturer ...
Страница 6: ...6 Chapter 2 Description of machine Picture 2 arm extension drawing ...
Страница 15: ...15 7 2 EXPLODED DRAWING OF MAICHINE ...
Страница 16: ...16 Circuit diagram 220V ...
Страница 17: ...17 Circuit diagram 380V ...