background image

Instructions

8510280P01AA - AN233086441027en-000501 | 3

© Danfoss | DCS (CC) | 2021.03

technique and vent piping with nitrogen gas 
flow.

 •  

Connect the required safety and control 
devices. 

5 – Leak detection

 Never pressurize the circuit with oxygen or dry 

air. This could cause fire or explosion.
  •   Do not use leak detection dye.
 •  

Perform a leak detection test on the complete 
system.

  •   The test pressure must not exceed:

Maximum compressor test 

pressure (Low side)

30 bar for 

VZH028-044

33.3 bar for 

VZH052-065

Maximum compressor test 

pressure (High side) 

41.1 bar

Maximum pressure difference 

between high side and low side 

of the compressor 

36 bar

 •   When a leak is discovered, repair the leak and 

repeat the leak detection.

6 – Vacuum dehydration

 •  

Never use the compressor to evacuate the 
system.

 •  Connect a vacuum pump to both the LP & HP sides.
 •   Pull down the system under a vacuum of 500 

µm Hg (0.67 mbar) / 0.02 inch Hg absolute.

  •   Do not use a mega ohmmeter nor apply power 

to the compressor while it is under vacuum as 
this may cause internal damage.

7 – Electrical connections

  •   Switch off and isolate the main power supply.
  •   Before touching any potentially live part of the 

drive, wait at least 4 minutes.

 •  The compressor is protected against excess 

current by the frequency converter. Follow 
local regulations regarding power line 
protection.The compressor must be connected 
to ground.

 •  

Use 6.3 mm tabs for quick connect spade 
terminals.

  •   Use a self-tapping screw to connect the ground 

conductor to the compressor.

 •  

Care must be taken during installation to 
ensure that the compressor operates in the 
correct direction. T1 (U), T2 (V) and T3 (W) 
terminals of compressor and drive U, V, W must 
match. Please refer to drawings for typical 
wiring connections and examine the specific 
wiring diagram located in the frequency 
converter package. For further details, refer to 
the application guidelines.

 •  Mounting: The base frame of the frequency 

converter must be very well fixed to the 
support to ensure a very good continuity 
between the ground potential of all electrical 
panels and electrical boxes of the system.

 •  

Wiring: All control wires have to be of a 
screeened design. The cable for electrical 
motor supply has to be of a shielded design as 
well. Correct earthing of the shield cover has to 
be done using the method shown on drawings, 
every time this one has to be earthed on each 
end of the cables. Distinct cable trays must be 
used for control and motor supply.

• The frequency converter ensures direct motor 
protection and the factory set parameters 

are such to protect the motor over all current 
malfunctions.
An external overload is not necessary.
• Set the frequency converter parameters in
accordance with Danfoss recommendations
for the CDS frequency converter and VZH
variable speed compressor.
 •  

Refer to variable speed drive manual for 
electrical connections details and installation.

 •  Compressor motor protection is provided by 

the variable speed drive. 

8 – Filling the system

  •   Keep the compressor switched off.
 •  

Fill the refrigerant in liquid phase into the 
outlet of the condenser or the liquid receiver. 
The charge must be as closed as possible 
to the nominal system charge to avoid low 
pressure operation and excessive superheat. 
For VZH028-044, the refrigerant charge limit is 
3.6 kg, For VZH052-065, the refrigerant charge 
limit is 5.4 kg. Above this limit; protect the 
compressor against liquid flood-back with a 
pump-down cycle not lower than 1.18 bar (g) 
for VZH028-044/1.8 bar (g) for VZH052-065 or a 
suction line accumulator.

 •  Never leave the filling cylinder connected to 

the circuit.

9 – Verification before commissioning

 Use safety devices such as safety pressure 

switch and mechanical relief valve in compliance 
with both generally and locally applicable 
regulations and safety standards. Ensure that 
they are operational and properly set. 

 Check that the settings of high-pressure 

switches do not exceed the maximum service 
pressure of any system component.
 •  A low-pressure switch is mandatory to avoid 

vacuum operation. Minimum setting 1.0 bar (g) 
for VZH028-044. Minimum pressure 1.5 bar for 
VZH052-065.

 •  

Verify that all electrical connections are 
properly fastened and in compliance with local 
regulations.

 •  

When using discharge temperature sensor, 
ensure that the discharge temperature sensor 
is correctly installed and fitted to the discharge 
piping (6 inches from discharge fitting) and 
well connected, especially after maintenance 
operations.

  •   After comissioning it is strongly recommended to 

keep the frequency converter always energized.

10 – Start-up

  •   Never start the compressor when no refrigerant 

is charged.

 •   Do not provide any power to the drive unless 

suction and discharge service valves on 
compressor are open, if installed.

  •   Energize the drive. The compressor must start, 

according to defined ramp-up settings. If 
the compressor does not start, check wiring 
conformity.

 •  Check the frequency converter control panel: 

If any alarm is displayed check the wiring and 
in particular the polarity of the control cables. 
If an alarm is shown, refer to the frequency 
converter application manual. Verify in 
particular the combination of compressor, 
frequency converter and refrigerant.

 •   Check current draw and voltage levels on the 

mains. The values for the compressor electrical 
motor can be directly displayed on the 
frequency converter control panel.

  •   The optimum compressor suction superheat is 

around 6K. The maximum allowed superheat is 
30K.

 •  Eventual reverse rotation can be detected by 

following phenomena; the excessive noise, 
no pressure differential between suction 
and discharge, and line warming rather than 
immediate cooling. A service technician should 
be present at initial start-up to verify that 
wiring from drive to compressor is properly 
phased and that the compressor is rotating in 
the correct direction. 

 •  Note that a 300 seconds period is necessary 

between 2 starts, a shorter period will be not 
allowed by the drive. The minimum running 
time is 12s for each start.

11 – Check with running compressor

 Check current draw and voltage. Measurement 

of amps and volts during running conditions must 
be taken at other points in the power supply, not 
in the compressor electrical box.
 •  

Check suction superheat to reduce risk of 
slugging.

 •  

Observe the oil level at start and during 
operation to confirm that the oil level remains 
visible. Excess foaming in oil sight glass 
indicates refrigerant on the sump.

 •  Monitor the oil sight glass for 1 hour after 

system equilibrium to ensure proper oil return 
to the compressor. This oil check has to be 
done over the speed range to guarantee:

  -   a good oil return at low speed with minimum 

gas velocity.

  -   a good oil management at high speed with 

maximum oil carry over.

  •   Respect the operating limits.
 

•  

Check all tubes for abnormal vibration. 
Movements in excess of 1.5 mm / 0.06 inch 
require corrective measures such as tube 
brackets.

 •  When needed, additional refrigerant in liquid 

phase may be added in the low-pressure side 
as far as possible from the compressor. The 
compressor must be operating during this 
process.

  •   Do not overcharge the system.
  •   Never release refrigerant to atmosphere.
 •  Before leaving the installation site, carry out 

a general installation inspection regarding 
cleanliness, noise and leak detection.

 •   Record type and amount of refrigerant charge 

as well as operating conditions as a reference 
for future inspections.

  •   Compressor failure to build up pressure: Check 

all bypass valves in the system to ensure that 
none of these has been opened. Also check 
that all solenoid valves are in their proper 
position.

 •  Abnormal running noise: Ensure the absence 

of any liquid flood-back to the compressor by 
means of measuring the return gas superheat 
and compressor sump temperature. The sump 
should be at least 6K above the saturated 
suction temperature under steady-state 
operating conditions.

 •  

The high-pressure switch trips out: Check 
condenser operations (condenser cleanliness, 
fan operation, water flow and water 

Отзывы: