
8.4 Checking the AC Drive after Commissioning
Context:
Before starting the motor, do these checks.
Procedure
1.
Make sure that all the START and STOP switches that are connected to the control terminals are in the STOP position.
2.
Make sure that the motor can be started safely.
3.
Activate the Start-up wizard. See the relevant application guide.
4.
Set the maximum frequency reference (that is, the maximum speed of the motor) to agree with the motor and the device that is
connected to the motor.
Commissioning
Operating Guide | VACON® 100 Wall-mounted Drives
AQ298036140958en-000101 / DPD01711
94 | Danfoss A/S © 2019.05