Danfoss
FT1555-BM bench mount capping machine Operator’s Manual
6 | © Danfoss FT1555-BM bench mount capping machine Operator’s Manual | 2023.03.
AQ445452814730en-000101
Installation / environment
Step 4:
Set the Main Power On/Off switch to the On position.
Note: Power Switch will illuminate green when power is on.
(See Figure 4).
Step 5:
Turn the Heater On/Off Timer clockwise past 10 minutes to desired
heat duration allowing for at least five minutes of preheat time.
(See Figure 5).
Note: White indicator light will illuminate when heater is activated.
Step 6:
Select the proper CapSeal capsule by measuring the end fitting
point to point on a hex style fitting or the measure the largest
outside diameter of the end fitting. (See Figure 6).
Step 7:
Reference the sizing chart on page 7 to determine the proper
CapSeal capsule.
Step 8:
Place CapSeal capsule over the end-fitting securely ensuring that
the fitting is fully inserted into the capsule. (See Figure 7).
Figure 5
Figure 6
Figure 4
Figure 7