User manual
Installation, Operation and Maintenance APP Pumps (APP 5.1-10.2)
11
180R9263 / IOM APP Pumps - v01 / 01.2013
5.1 Important dimensions
Physical dimensions and connections for the
pump unit are described in Data sheet,
appendix 1 .
5.2 Cleanliness
It is very important that the tubes and pipes are
completely clean
: no dirt, chips or burrs are
allowed . Flush all piping before connecting the
high pressure pump to ensure the system is
clean . Internal surfaces of the piping must not be
corroded . If dirt or rust is not removed, the pump
and the valves can be damaged and in the worst
case damaged beyond repair!
5.3 Fluid temperature
Before start-up, the fluid and pump housing
temperature must be above the minimum
start-up temperature, see Data sheet,
appendix 1 .
5.4 Electrical data
Check voltage, current frequency and rated
power on the electric motor and VFD setting
name plate on both the motor and the VFD .
5.5 Local regulations
Commissioning must always be done in
accordance with valid regulations and local
standards .
5.6 Pre mounting checklist, based on
Danfoss preferred system design
Schematic 1: Recommended system design
5.
Installation and
commissioning
M
Brine
Permeate
APP
Feed
1
2
3
5
4
5
7
6
Содержание APP 5.1
Страница 5: ...5 180R9263 IOM APP Pumps v01 01 2013 EU Declaration of Conform ity...
Страница 39: ...3 IOM Electric motors 180R9230 Electric Motors Motor Manual hoyermotors com Manual 180R9230...
Страница 53: ...6 Trouble shooting guide Guideline Trouble shooting guide for APP pumps MAKING MODERN LIVING POSSIBLE...
Страница 69: ...User manual Appendices for IOM APP Pumps APP 5 1 10 2 51 180R9263 IOM APP 5 1 10 2 Appendices v02 01 2013...