Commissioning and reboot
Observe before commissioning the DAS-300 E:
z
Unused bays must be fitted with dummy modules to maintain balanced airflow and
cooling.
z
The DAS-300 E must always be operated with two power supply modules and one fan
module.
z
Safe grounding must be provides for all power supply cables. Check the grounding of
the DAS-300 E before applying power.
z
Always operate the DAS-300 E using a UPS (uninterruptible power supply).
z
The power source must be protected against electrical overload.
8.1
Commissioning
The DAS-300 E is commissioned as part of a storage system. Thereby the following starting
order must be observed:
NOTE
Supply the storage system using a programmable socket strip
in order to ensure the starting order.
1. Connect both power supply module to the power supply.
The DAS-300E starts automatically.
The power on LED is lit green.
2. Start the commissioning of the DAS-303.
3. Start the commissioning of the recorder.
The recorder’s boot and initialization process extends for approximately 2 minutes because
of the controller initialization. After completing the whole system is ready for operation.
8.2
Reboot
When rebooting the system, the starting order described above must be observed absolutely.
There will be no recording if the recorder is commissioned before the DAS-303 / DAS-300 E.