Installation
EDUS391004-N
80
Installation of Outdoor Units
7-3 Leading wire Procedure
•
The power wiring and ground wiring are passed out from the power
wiring hole on the sides, the front (knock hole) or the bottom frame
(knock hole).
•
The transmission wiring is passed out from the wiring hole (knock
hole) on the front of the unit or from a piping hole.
(Refer to figure 17-1)
1.
Electric wiring diagram
Printed on the back of the electrical components box lid.
2.
Knockout hole
3.
Power line
4.
Transmission line
(Refer to figure 17-2)
1.
Electrical components box lid
2.
Service lid
3.
[Service precautions] Label location
NOTE
•
Open the knock holes with a hammer or the like.
•
After knocking out the holes, we recommend you remove any burrs
and paint them using the repair paint to prevent rusting.
(Refer to figure 17-1, 2)
•
When passing wiring through the knock holes, remove burrs
around the knock holes and protect the wiring with protective tape.
(Refer to figure 17-1, 2)
•
If small animals might enter the unit, block off any gaps (hatching
parts in figure 17-1, 2) with material (field supply).
7-4 Transmission Wiring Connection Procedure
•
Referring to figure 18 connect the transmission wiring between
outdoor unit and indoor unit, outdoor unit and outdoor unit of other
system, outdoor unit and outdoor unit of same system.
(Refer to figure 18)
1.
Electrical components box (1)
2.
Electrical components box (2)
3.
Do not open the electrical components box (2) lid.
(There are no work when installation)
4.
Never connect the power wire.
5.
To outdoor unit of other system
6.
Use duplex wires (No polarity)
7.
Branch Selector unit
8.
Indoor unit
9.
Indoor unit (Cooling only)
NOTE
•
Do not connect the power wiring to terminals for the transmission
wiring. Doing so would destroy the entire system.
•
When connecting wires to the terminal block on the PC-board, too
much heat or tightening could damage the PC-board. Attach with
care.
See the table below for the tightening torque of the transmission
wiring terminals.
•
Transmission wiring (About the symbol
~
,
see figure 18
)
should be done within the following limitations.
If they are exceeded, transmission problems may occur.
Between outdoor unit and Branch Selector (or indoor) unit
Between Branch Selector unit and indoor unit
Between outdoor unit and outdoor unit of other systems
Max. wiring length
: 3280 ft
Max. total wiring length
: 6560 ft
Max. no. of branches
: 16
[Note]
No branch is allowed after branch (
See figure 19
)
Max. no. of outdoor units of other system
that can be connected
: 10
(Refer to figure 19)
1.
Branch
2.
Branch after branch
Between outdoor unit and outdoor unit of same system
Max. wiring length
: 100 ft
•
The transmission wiring inside the electrical components box
should be secured using the clamp (1) as shown in figure 20.
(Refer to figure 20)
1.
In the electrical components box
2.
Retain to the electrical components box with the accessory
clamp (1).
3.
Vinyl tube (accessory)
•
Outside the units, the transmission wiring must be finished
simultaneously with the local refrigerant piping, and wound with
tape (field supply) as shown in figure 21.
(Refer to figure 21)
1.
Suction gas pipe
2.
HP/LP gas pipe
3.
Liquid pipe
4.
Insulation material
5.
Finishing tape
6.
Transmission wiring
•
Wiring to other systems should be connected to terminals F1 and
F2 (TO OUT/D UNIT) on the PC-board of the electrical
components box (1).
7-5 Power Wiring Connection Procedure
•
Be sure to connect the power supply wiring to the power supply
terminal block and hold it in place using the included clamp as
shown in the figure 22.
•
The L1, L2, L3 and N phases of the power wiring should be
secured separately to the hook using the included clamp (1).
•
The ground wiring should be bound to the power wiring using the
included clamp (1) to prevent outside force from being applied to
the terminal area.
(Refer to figure 22)
1.
Power supply
(MODEL PBYD:3~460V 60Hz)
(MODEL PBTJ:3~208/230V 60Hz)
2.
Earth leakage circuit breaker
3.
Branch switch, Overcurrent breaker
4.
Ground wire
5.
Electrical components box (1)
6.
Electrical components box (2)
7.
Do not open the electrical components box (2) lid.
(There are no work when installation)
8.
Attach insulation sleeves
9.
Power supply terminal block
10.
Ground terminal
11.
Clamp (1) (accessory)
12.
Vinyl tube (accessory)
CAUTION
•
Be sure to use crimp-style terminal with insulating sleeves for
connections. (See the figure below.)
•
For wiring, use the designated power wire and connect firmly, then
secure to prevent outside pressure being exerted on the terminal
board.
•
Use an appropriate screwdriver for tightening the terminal screws.
A screwdriver with a small head will strip the head and make
proper tightening impossible.
Screw size
Tightening torque (ft · lbf)
M3.5 (A1P)
0.59 ~ 0.71
1
2
1
2
Power wire
Crimp-style terminal
Insulating sleeve
3P215731-12R
Содержание VRV III REMQ120PBTJ
Страница 1: ...EDUS 391004 N AMERICAS AMERICAS Installation...
Страница 24: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 23 1P218719...
Страница 25: ...REFNET Pipe System EDUS391004 N 24 Installation of Outdoor Units 1P218720...
Страница 26: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 25 1P218720...
Страница 28: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 27 1P280278A...
Страница 29: ...REFNET Pipe System EDUS391004 N 28 Installation of Outdoor Units 1P280278A...
Страница 30: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 29 1P280279...
Страница 33: ...REFNET Pipe System EDUS391004 N 32 Installation of Outdoor Units 1P218714...
Страница 34: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 33 1P218714...
Страница 35: ...REFNET Pipe System EDUS391004 N 34 Installation of Outdoor Units 1P218715...
Страница 36: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 35 1P218715...
Страница 38: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 37 3D071080...
Страница 39: ...REFNET Pipe System EDUS391004 N 38 Installation of Outdoor Units 1P280510A...
Страница 40: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 39 1P280510A...
Страница 41: ...REFNET Pipe System EDUS391004 N 40 Installation of Outdoor Units 1P280511A...
Страница 42: ...EDUS391004 N REFNET Pipe System Installation of Outdoor Units 41 1P280511A...
Страница 113: ...EDUS391004 N Field Setting Installation of Outdoor Units 113 2P281604A...
Страница 114: ...Field Setting EDUS391004 N 114 Installation of Outdoor Units 2P281604A...
Страница 115: ...EDUS391004 N Field Setting Installation of Outdoor Units 115 2P281604A...
Страница 116: ...Field Setting EDUS391004 N 116 Installation of Outdoor Units 2P281604A...
Страница 117: ...EDUS391004 N Field Setting Installation of Outdoor Units 117 RXYQ72PBYD RXYQ96PBYD RXYQ120PBYD 3P281590...
Страница 121: ...EDUS391004 N Field Setting Installation of Outdoor Units 121 2P281605A...
Страница 122: ...Field Setting EDUS391004 N 122 Installation of Outdoor Units 2P281605A...
Страница 124: ...Field Setting EDUS391004 N 124 Installation of Outdoor Units 2P281605A...
Страница 129: ......